Join us for the Virtual Ribbon Cutting for the Scott Rd/I-215 Project LIVE on our Facebook or Twitter on September 17 at 9:30AM. www.twitter.com/rivcotrans or www.facebook.com/rivcotrans
Crews are paving the northbound I-215 freeway lanes in the project area with intermittent closures Monday through Thursday nights, April 20-23, from 8 p.m. to 6 a.m. The southbound lanes will be paved Friday night from 8 p.m. to 9 a.m., and Monday through Wednesday nights next week from 8 p.m. to 6 a.m. Crews are also finishing civil and electrical work to open the loop ramps on Thursday morning, April 23. Please note, only the new loop ramps will be open to motorists, the existing northbound off-ramp and southbound on-ramp will be closed for construction through April 30. Scott Road will be closed to through traffic on Wednesday night, April 22 from 8 p.m. to 6 a.m.
Weather permitting, work continues on the new 1-215 northbound loop off-ramp and southbound loop on-ramp. All the concrete paving is completed and crews are installing the guardrail, rock blanket for erosion control, and completing lighting and the drainage system. Motorists may notice new signage for the ramps in preparation for an early Spring opening. Work will also be completed on the I-215 in the center median and along the new loop ramp merge lanes where crews are completing slope paving on the east and west sides of the bridge. Construction Update On Scott Road, crews will continue working on the final curb and gutter, asphalt pavement, signs, electrical signals and finish grading work.
For more information regarding this project, please visit www.cityofmenifee.us/scottrdinterchange
Nighttime Scott Road lane closure Friday and Saturday.
No planned freeway lanes or ramp closures
One lane on Scott Road near both Antelope and Haun roads will be closed between 8 pm and 5 am on Friday and Saturday nights, October 4 and 5. One lane will remain open for through traffic. There are no freeway lane or ramp closures expected this week.
During daytime work hours, crews will continue working on the barrier fence, placing concrete and continue installing the rock blanket near the southbound off-ramp at Scott Road. Crews also will continue placing concrete for the new sidewalk, curb and gutter on Scott Road and continue earthwork and hauling operations for the new loop ramps.
CONSTRUCTION HOTLINE: (951) 215-2288
Project Website: cityofmenifee.us/ScottRdInterchange
A large gathering celebrated the start of construction at the Scott Road/Interstate 215 Interchange groundbreaking ceremony today in Menifee. The $57.8 million project will improve I-215 freeway access and traffic flow on Scott Road, an important east/west connector in Southwest Riverside County. Visit city of http://cityofmenifee.us/495/Scott-RoadI-215-Interchange-Project for details.