We completed all concrete curb & gutter and sidewalk in the Carver Tract area. The contractor is working on adjusting affected fences, gates, and other facilities. We are experiencing a delay with material for underground storm drain detention system. The contractor will clean and secure the project site prior to stop the construction. Please use caution while driving/walking through the area. Construction NOTICE (pdf)
We are continuing the application of slurry seal to Hemet, San Jacinto, and French Valley areas. Please follow traffic control signs and lane closures on Domenigoni Parkkway and Murrieta Hot Springs Road. Please expect delays and “DO NOT” drive over wet slurry material. Thank you for your patience and understanding.
The resurfacing on Leon Road from Jean Nicholas Road to Briggs Road and a major portion of Max Gilliss Boulevard from Leon Road to Winchester Road has been completed. The contractor applied a first coat of traffic stripe paint and is scheduled to apply a second coat of traffic stripe paint & pavement markings in the next two weeks. Please continue use caution while travelling through this area. New proposed Clinton Keith Road connecting Leon Road to Winchester Road (at Benton Road) is progressing well and still on schedule.
We are making good progress for the construction of proposed sidewalk on Carmen Avenue and Broadway Street in the Cabazon area. The contractor is working on the roadway improvements and clean up. Please continue use caution while travelling through this area.
We are actively working in the Hemet areas. This includes applying chip seal and slurry seal. Please do not park on your street on posted date and do not drive after the installation of new fresh slurry until we open the road. For more information, please check our website at www.rcprojects.org/slurryseal
https://player.vimeo.com/video/702092455?h=db0b56852a"
We completed 95% the replacement of existing asphalt pavement on Leon Road and Max Gilliss Blvd. in the Winchester/French Valley area. The contractor is schedule to apply paint Traffic Stripe on Tuesday. April 26, 2022. Please use caution while driving on Leon Road and Max Gilliss Boulevard due to pending traffic stripe work. The new proposed Clinton Keith Road connecting from Leon Road to Winchester Road is also progressing well with the construction of retaining walls and a bridge while mitigating some environmental concerns.
We are applying chip seal and slurry seal in Hemet area this week. Please do not park on your street on posted date and do not drive after the installation of new fresh slurry until we open the road. For more information, please check our website at www.rcprojects.org
Washington Street at Saddleback Road is still under construction for new proposed Traffic Signal. We experienced a little delay due to boulders/large rocks at new signal pole foundations. As always, please use caution while travelling through. There will be flaggers to control traffic as required. Thank you for your patience and understanding.
We just paved new asphalt on Leon Road from Jean Nicholas to Briggs Road. Traffic stripe and pavement markings are to be scheduled within two weeks. Please use caution while travelling through. Max Gilliss Blvd. is also under repaving, expect traffic delays during rush hours. Thank you for your patience and understanding.
We are currently working on the construction of a new sidewalk on Broadway Street from Carmen Avenue to Bonita Avenue in the Cabazon area. Please continue to use caution and follow instructions from flagger controlling traffic. Thank you for your patience.
We are removing traffic stripes and markings on various streets to clean and prepare for slurry seal or chip seal applications, and replacement of existing concrete curb ramps in Homeland and Hemet areas. Please observe “No Parking” signs posted with date of slurry seal operation. During this date, your street will be closed until the new surface is dried for traffic. Please protect our new pavement surface by NOT Driving on wet slurry seal and NO Turning vehicle while stopped (this will cause steering scar on the new surface). For more information, please read information provided prior to slurry application to your street and our web site
We are experiencing delays due to unforeseen conditions at the project site and working on solutions. The traffic signal work will continue on April 18, 2022 and expect to complete mid-May. Thank you for your patience and understanding. Please continue use caution while travelling on Washington Street at Saddleback Road in the Woodcrest area.
We are currently working on concrete placement for sidewalk and driveways on various streets in the Carver Tract area. Due to concrete shortage and rationing, contractor will place as much concrete sidewalk as possible. Thank you for your patience and continue use caution while traveling through the work zone.
We are continuing with the construction of proposed sidewalk in the Carver Tract Area. Due to availability of concrete, the contractor scheduled as much as possible for the placement of concrete for sidewalk panels. Thank you for your cooperating and understanding. Please use caution while travelling through this neighborhood.