We replaced close to a half mile of asphalt pavement with one layer of new asphalt on Long Canyon Road from Quail Trail towards Dillon Road in the Community of Southeast Desert Hot Springs. Next week, the contractor will continue removing existing asphalt pavement and replacing with new asphalt for about 3/4 mile. Please observe construction warning signs and use caution while travelling through the work zone.
#jurupagradeseparationproject
#jurupavalleyca
@CityofJurupaValley
CURRENT UPDATE
Week of March 4
Felspar Street north of Jurupa Road
Monday - Wednesday
6 a.m. - 4 p.m.
Actualización actual
Semana del 4 de marzo
Felspar Street al norte de Jurupa Road
Lunes - miercoles
6 a.m. a 4 p.m.
PROJECT PROGRESS
Construction continues on 6 new storm drain catch basins on Felspar Street north of Jurupa Road, weather permitting. Please note the "No Parking" signs and sidewalk closures/detours for pedestrians. ALL BUSINESS ACCESS IS OPEN.
PROGRESO DEL PROYECTO
La construcción continúa en 6 nuevas cuencas de captura de drenaje pluvial en la calle Felspar al norte de Jurupa Road, lo que lo permite el clima. Tenga en cuenta las señales de estacionamiento "sin estacionamiento" y los cierres/desvíos para los peatones. TODO EL ACCESO EMPRESARIAL ESTÁ ABIERTO.
The contractor is continuing with the construction to complete contract work and improvements including drainage systems. Please continue to use caution and observe construction warning signs. Thank you for your patience and understanding!
We just started the reconstruction of Long Canyon Road from Dillon Road to Quail Trail in the Community of Southeast Desert Hot Springs. Anticipated completion is April 2024. Please observe construction warning signs and use caution while travelling through the work zone.
CURRENT UPDATE
Week of February 26
Felspar Street north of Jurupa Road
Monday - Friday
6:30 a.m. - 3 p.m.
Actualización actual
Semana del 26 de febrero
Felspar Street al norte de Jurupa Road
Lunes Viernes
6:30 a.m. a 3 p.m.
PROJECT PROGRESS | PROGRESO DEL PROYECTO
Construction continues on 6 new storm drain catch basins on Felspar Street north of Jurupa Road, weather permitting.
Please note the No Parking signs and sidewalk closures/detours for pedestrians.
La construcción continúa en 6 nuevas cuencas de captura de drenaje pluvial en la calle Felspar al norte de Jurupa Road, lo que lo permite el clima.
Tenga en cuenta las señales de estacionamiento sin estacionamiento y los cierres/desvíos para los peatones.
We are continuing with the pavement rehabilitation project to Johnston Avenue from San Jacinto Street to Stanford Street in the East Hemet area. Contractor is working on asphalt dike along the road and preparing for the installation of traffic stripe and pavement markings. Please use caution and observe construction warning signs while travelling through the work areas. Thank you for your patience and understanding!
The contractor is continuing with hauling debris to disposal sites and cleaning up the areas (weather permitting). The road/bridge is no longer accessible for traffic as well as pedestrians. Please DO NOT ENTER the demolished area.
Clinton Keith Road connecting Leon Road and Winchester Road (SR 79) in the French Valley/City of Murrieta is OPEN. The contractor is continuing with the construction to complete contract work and improvements. Please continue to use caution and observe construction warning signs. Thank you for your patience and understanding!
We completed with the pavement rehabilitation to Johnston Avenue from San Jacinto Street to Stanford Street in the East Hemet area. Due to recent rain events and forecasted rain, no construction work scheduled for next week. Please continue to use caution and observe construction warning signs while travelling through the work areas. Thank you for your patience and understanding!
Clinton Keith Road connecting Leon Road and Winchester Road (SR 79) in the French Valley/City of Murrieta is OPEN. The contractor is continuing with the construction to complete contract work and improvements. Please continue to use caution and observe construction warning signs. Thank you for your patience and understanding!
DAYTIME ROAD CLOSURE: TRAFFIC IMPACTS
Detroit Street will be closed to through traffic at Hamner Avenue during daytime work.
Tuesday - Thursday
Feb. 6 -8
9 a.m. to 3 p.m.
Use alternate routes, add extra time for travel, and follow detour for local access.
PROJECT REMINDER:
REDUCE SPEED to 35 mph in the project area, watch for crews working on the shoulder from Detroit to Citrus streets, along the length of the bridge, and in the center median from Alhambra to Detroit streets.
NO PEDESTRIAN ACCESS across the bridge
USE @RiversideTransitAgency ROUTE 3
Check out RTA’s website for more information https://www.riversidetransit.com/
Route 3:
https://www.riversidetransit.com/.../Route%203%20%7C...
SUBSCRIBE at http://www.hamneraveproject.com/updates/
STAY CONNECTED on IG @hamneraveproject and on FB @Hamner Avenue Bridge and Widening Project.
JURUPA ROAD GRADE SEPARATION Project ROAD CLOSURE EXTENDED through February 13 due to weather.
We removed 100% of Whitewater Cutoff Bridge. The contractor is continuing with hauling debris to disposal sites and clean up the areas. The road/bridge is no longer accessible for traffic as well as pedestrians. Please DO NOT ENTER the demolished area.
We removed 100% of Whitewater Cutoff Bridge. The contractor is continuing with hauling debris to disposal sites and clean up the areas. The road/bridge is no longer accessible for traffic as well as pedestrians. Please DO NOT ENTER the demolish area.
We are continuing with the pavement rehabilitation project to Johnston Avenue from San Jacinto Street to Stanford Street in the East Hemet area. The contractor is scheduled to finish the final asphalt surface from Columbia Street to San Jacinto Street this week (weather permitting). To avoid delays please use alternate routes. Please use caution and observe construction warning signs while travelling through the work areas. Thank you for your patience and understanding!