Ramona Avenue Resurfacing

Limits: Nuevo Road to Stalder Avenue
Length: Approximately 800 feet
District: 5
Community: Nuevo

The County of Riverside Transportation Department is proposing to resurface approximately 800 feet of Ramona Avenue from Nuevo Road to Stalder Avenue. Ramona Avenue is classified as a local road in the County of Riverside’s General Plan. Ramona Avenue is a two lane road and currently ranges from 23-25 feet wide. The proposed project will remove existing asphalt and place back with Hot Mix Asphalt (HMA).


Additional improvements include:

  • Construction of driveways

  • Reconstruction of asphalt concrete dike

  • Utility adjustments

  • Striping of roadway, including pavement markers and reflectors

  • Salvage/removal and installation of new signs

No additional right-of-way, permits to enter and construct (PEC), or temporary construction easements (TCE) will be required to construct the proposed improvements.

PROJECT SCHEDULE

Environmental Clearance:
April 2021
Final Design: February 2021
Construction Start: September 2021
Construction Completion: November 2021