Grand Avenue Resurfacing

Limits: Plumas Street to Patrick Court
Length: Approximately 5,000 feet
District: 1
Community: Lake Elsinore

The County of Riverside Transportation Department is proposing to resurface approximately 5,000 feet of Grand Avenue from Plumas Street to Patrick Court. Grand Avenue is classified as a Major Highway in the County of Riverside’s General Plan. Grand Avenue is a four lane road and currently ranges from 38’-78’ wide with mostly curb and gutter. The proposed project will include milling the existing Asphalt Concrete (AC) pavement down and repaving with Hot Mix Asphalt (HMA) and Rubberized Hot Mix Asphalt (RHMA). A portion of the existing roadway will only be overlaid with RHMA.


Additional improvements include:

  • Reconstruction of concrete cross gutter, spandrel, curb/gutter, and non ADA compliant curb ramps

  • Reconstruction of asphalt concrete dike

  • Placement of safety edge and shoulder backing

  • Utility adjustments

  • Striping of roadway, including pavement markers and reflectors

  • Salvage/removal and installation of new signs

  • Relocate pedestrian crossing buttons

No additional right-of-way, permits to enter and construct (PEC), or temporary construction easements (TCE) will be required to construct the proposed improvements. The project improvements will raise most of the existing roadway profile by 0.15 feet.

PROJECT SCHEDULE

Environmental Clearance:
November 2020
Final Design: December 2020
Construction Start: July 2021
Construction Completion: September 2021