Connecting Our Communities

News

Project News

San Jacinto Avenue Resurfacing - Weekly Newsletter

We are currently reconstructing concrete cross-gutters crossing San Jacinto Avenue from Stetson Avenue to Florida Street in Hemet area. The roadway is narrow, please use caution while travelling through. Suggest to use alternate route.

Steven Gray
Thousand Palms Canyon Road Resurfacing - Weekly Newsletter

We completed the pulverizing of existing pavement and pave new asphalt (base course) on Thousand Palms Canyon Road from Dillon Road to Washington Street/Ramon Road. Contractor is paving new surface course this week and scheduled to complete on Monday, 18 July 2022. Please observe construction warning signs and follow traffic control personnel (flaggers). Thank you for your patience and understanding.

Steven Gray
El Toro Road and Dexter Avenue Sidewalk - Weekly Newsletter

We are currently working on the construction of Curb & Gutter along El Toro Road and east side of Dexter Avenue in the North Lake Elsinore area. Please observe “OPEN TRENCH” and use caution while travelling through this area. Thank you for your patience and understanding.

Steven Graydexter
Jurupa Grade Separation Project Construction Update 7/11/22

Crews continue to work extended hours on the sewer line installation on Felspar Street near Jurupa Road.  Construction on the  storm water pump station in the same vicinity continues to progress. Crews continue work  on the new Van Buren Boulevard bridge which includes excavation work to lower Jurupa Road. 

This week, Monday through Friday, July 11- 15, from 8 p.m. to 7 a.m., the intersection of Felspar St. and Jurupa Rd. will be closed during nighttime work. Additionally, crews may need to close shopping center driveways but will keep access open by closing only one at a time. Please use Pedley Rd. and Galena St. for the detour to access Felspar St. BUSINESS ACCESS REMAINS OPEN.

#JurupaGradeSeparationProject

BUSINESS ACCESS REMAINS OPEN:

ROAD CLOSURE: Week of JULY 11

Monday - Friday nights | from 8 p.m. - 7 a.m.

Intersection closure at Jurupa Rd. and Felspar St.

Please use Pedley Rd. and Galena St. for the detour to Felspar St.

 

TRAFFIC CONTROL: Week of JULY 11

Monday - Friday nights | from 8 p.m. - 7 a.m.

NB and SB Felspar St. just north of Jurupa Rd. 

Drive with caution in the area. 

 

Crews may need to close shopping center driveways but will keep access open by closing only one at a time. 

 

 SUBSCRIBE to WEEKLY UPDATES http://www.JurupaGradeSeparation.com

Steven Gray
Clinton Keith Rd Video Update Construction Notice July 11-15

Los Alamos Road from Menifee Road to Briggs Road/Leon Road is CLOSED to through traffic. Please follow detour signs. We are currently working on proposed Brigg Road Realignment to provide access from Los Alamos Road to Winchester Road via Porth Road. Contractor is scheduled to replace asphalt pavement (grind and pave) at Max Gilliss Blvd. & Winchester Road on July 14, 2022. Thank you for your patience and understanding.

Slurry Seal FY 21-22 Dist. 1 - Weekly Newsletter

The Slurry Seal application to various streets in District 1 of Riverside County is now completed. The contractor is performing minor repairs to damaged areas, scheduling to complete concrete curb ramps and paint traffic stripe as soon as possible.

Steven Grayslurryseal
Mayberry Avenue Sidewalk - Weekly Newsletter

We recently started the construction of new proposed sidewalk along Mayberry Avenue from Pear Tree Lane to Casino Road in the Valle Vista area. The project is anticipated to complete early August 2022. Please use caution while travelling through the work zone and expect a little delays.

Steven Gray
Slurry Seal FY 21-22 Dist. 1 - Weekly Newsletter

We are currently applying slurry seal to various streets in the Perris areas. Please DO NOT drive over wet slurry seal material and observe construction warning signs. Thank you for your understanding.

Contractor is installing CAT track (layout) for Traffic Stripe on Grand Ave. in Lake Elsinore/Lakeland Village today. County Traffic staff is reviewing and should approve the CAT track by tomorrow. The contractor is scheduled to apply first coat of traffic paint this Saturday 7/2. Final coat shall be scheduled.

Steven Grayslurryseal
Clinton Keith Video Construction Update July 5th-8th

We are currently working with the contractor to properly close Briggs Road from Leon Road to Los Alamos Road for the construction of new proposed Clinton Keith Road. A portion of the roadway on Los Alamos Road and Briggs Road is now a dirt road. Please use caution while travelling through. Contractor is actively progressing with the construction of a bridge, retaining walls, and earth work for new proposed Clinton Keith Road from Leon Road to Winchester Road in the French Valley area.

Dexter Ave. & El Toro Rd. Sidewalk Weekly Update - 07/05/22

This week the County is removing existing asphalt pavement and ground for the new proposed sidewalk along El Toro Road in front of Temescal Canyon High School.. Please use caution while traveling through the work zone.

 

Yvette Munozdexter
Dexter Ave and El Toro Rd Sidewalk - Weekly Newsletter

We are continuing the reconstruction of concrete cross-gutter, driveways, and new sidewalk on El Toro Road and Dexter Avenue. Please use caution while travelling through the work zone.

Steven Gray
Thousand Palms Canyon Road Resurfacing - Weekly Newsletter

7/5/22 Weekly Update

We are continuing the pulverizing of existing asphalt pavement and paving new asphalt to Thousand Palms Canyon Road from Ramon Road/Washington Street to Dillon Road in the Desert Hot Springs area. Please observe construction warning signs and follow flagger’s (traffic control person) instructions while travelling through this area. Thank you for your patience and understanding.

6/29/22 Weekly Update

We are currently paving new asphalt and pulverizing existing asphalt pavement on Thousand Palms Canyon Road. These operations are about a mile apart with multiple Traffic Control crews. Please use caution and expect delays while using Thousand Palms Canyon Road.

Steven Gray
Briggs Rd Closure / Clinton Keith Road Phase 3 and Leon Rd & Max Gilliss Blvd Resurfacing - Weekly Newsletter

Starting June 28, 2022, the contractor is scheduled to “Permanently Closed” Briggs Road from Leon Road to Los Alamos for the construction of new Clinton Keith Road. Los Alamos Road from Menifee Road to Briggs Road is access for local traffic/residents and emergency vehicles ONLY. We are also working on new alignment for Briggs Road from Los Alamos Road to Porth Road and Winchester Road. Please follow detour signage and thank you for your understanding.

Dexter Ave. & El Toro Rd. Sidewalk - Weekly Status

We are starting the construction of new proposed sidewalk along El Toro Road and Dexter Avenue towards City of Lake Elsinore limits. The contractor completed the curb ramps replacement front of Temescal Canyon High School. The contractor is currently removing existing asphalt pavement and ground along the west side of Dexter Avenue from El Toro Road to Costco shopping center. Please use caution while travelling on Dexter Avenue because of “Open Trench” along the shoulder.

Steven Gray
San Jacinto Ave. Resurfacing - Weekly Status

We are starting the reconstruction of San Jacinto Ave from Florida Avenue to Thornton Avenue in Hemet area. The contractor is currently removing and replacing concrete Curb Ramps, Spandrels, Cross-Gutters, and Curb & Gutter along San Jacinto Avenue. Please use caution and observe construction warning signs while travelling through this area. Thank you for your understanding and patience.

Steven Gray