Slurry Seal FY21-22 District 1, Weekly Update

We are currently applying slurry seal to various streets in the Woodcrest and La Sierra areas. Please observe “No Parking” signs posted with the date of operation. Also, please do not drive over wet slurry and wait for the contractor to open the street as soon as the new slurry seal material dried for traffic.

Clinton Keith Road Construction Notice for week of May 31-June 3

The contractor is scheduled to install all Thermoplastic Pavement Markings on Leon Road from Jean Nicholas Road to Max Gilliss Blvd. and on Max Gilliss Blvd. There will be lane closures, please use caution while travelling through this area. For Clinton Keith Road: The contractor is continuing the construction of a new proposed bridge crossing French Valley Creek.duled to install all Thermoplastic Pavement Markings on Leon Road from Jean Nicholas Road to Max Gilliss Blvd. and on Max Gilliss Blvd. There will be lane closures, please use caution while travelling through this area. For Clinton Keith Road: The contractor is continuing the construction of a new proposed bridge crossing French Valley Creek.

Continue Briggs Rd realignment.
Continue retaining wall construction.
Construct abutment footings.
Pile driving for bridge foundation: Ongoing

For more project information, please visit www.clintonkeithphase3.org

Slurry Seal FY 21-22 Dist. 1 - Weekly Newsletter

We are currently applying new asphalt surface treatment (slurry seal) in the Woodcrest area of County of Riverside. Please observe “NO PARKING” signs posted with the date of slurry seal operation. Please plan on no parking or driving on these streets until the slurry material dried and the roadway is opened. For more information, please visit us on Facebook, and Twitter @RivcoTrans.

Steven Grayslurryseal
Washington Street at Saddleback Road Traffic Signal Update

The new proposed traffic signal system on Washington Street at Saddleback Road is fully functional as of May 19, 2022. The contractor is continuing with minor repair, other improvements, and clean up the project site. Please use caution while travelling on Washington Street at Saddleback Road due to new traffic patterns associated with new improvements.

Steven Gray
Slurry Seal Dist. 3 - Weekly Newsletter

We completed all slurry seal application to proposed streets in District 3 including Temecula, French Valley, Winchester, Hemet, Romoland, and Homeland areas. The contractor is scheduled to install traffic stripe and pavement markings as soon as possible. The contractor is still working on concrete curb ramps replacement at various areas in District 3. Please use caution while travelling through construction zone.

Steven Grayslurryseal
Clinton Keith Phase 3 Construction Notice and Video Update May 23-27

We are currently replacing wiring for new proposed Video Detection system to all Traffic Signals on Leon Road from Jean Nicholas/Baxter to Max Gilliss Blvd. in the French Valley area. The contractor is also scheduled to complete Pavement Delineations on Leon Road and Max Gilliss Blvd. next week. Lane closure and brief power outage for traffic signal system are expected during working hours. Please continue use caution while travelling through this area. Thank you for your patience and understanding.

For new proposed Clinton Keith Road from Leon Road to Winchester Road/Benton Road: The contractor is continuing with the construction of proposed Bridge over French Valley Creek.

Cajalco Road - Saturday Work

To minimize traffic impacts during regular weekday commute hours, our contractor is scheduled to work on Cajalco Road from Wood Road to Gustin Road in the Mead Valley & Lake Matthews area this Saturday, May 21, 2022. Working hours are from 7:00 AM to 5:00 PM. Crack sealing operations shall be controlled by flaggers. Please use caution and observe construction warning signs while travelling through this area. Thank you for your patience and understanding.

Washinton Street at Saddleback Road Traffic Signal - Weekly Status

The contractor and technical support staff are turning on the new proposed Traffic Signal on Washington Street at Saddleback Road today (May 17, 2022) in the Woodcrest area. The contractor is continuing to do some minor work and clean up. Please use caution while travelling through due to changes at this new signalized intersection. Thank you for your patience.

Steven Gray
Carver Tract Sidewalk project

We completed the proposed sidewalk, surface drainage structures, roadside signs, and fences & gates adjustment in the Carver Tract area. Contractor is waiting for material to construct a underground storm water detention basin on Luzon Street. Tentative schedule for this work is in July 2022.

Clinton Keith Phase 3 Construction Notice and Video Update

We are replacing electrical wiring for a new traffic signal video detection system on Leon Road from Jean Nicholas Road to Briggs Rd./Max Gilliss Blvd. During construction, the signal system will be off and the intersection will be an “ALL WAY” STOP. Please use caution and expect delays while approaching the intersection under construction.

Schedule is as follows:

Thursday 5/12 – Leon at Jean Nicholas (completed)

Friday 5/13 – Leon at Lantana

Monday, 5/16 – Leon at Penny Cress

Tuesday, 5/17 – Leon at Briggs/Max Gilliss

 

For newly proposed Clinton Keith Road from Leon Road to Winchester Road/Benton Road: The contractor is currently working on the construction of a Bridge and associated facilities in the middle of the project limits.

Slurry Seal FY 21-22 Dist. 1 - Saturday Work Update

To minimize the traffic impact during regular weekday travelling hours, the contractor is scheduled to crack sealing asphalt pavement on Washington Street from Van Buren Blvd. to Overlook Parkway in the Woodcrest area this Saturday, May 14. Traffic shall be reduced to ONE Lane/One direction and moved with the crack sealing operation, please observe warning signs and flagger’s instructions. Thank you for your understanding.

Steven Grayslurryseal
Carver Tract Sidewalk, Weekly Update - May 9, 2022

We completed all concrete curb & gutter and sidewalk in the Carver Tract area. The contractor is working on adjusting affected fences, gates, and other facilities. We are experiencing a delay with material for underground storm drain detention system. The contractor will clean and secure the project site prior to stop the construction. Please use caution while driving/walking through the area. Construction NOTICE (pdf)

Slurry Seal FY21-22 District 3, Weekly Update

We are continuing the application of slurry seal to Hemet, San Jacinto, and French Valley areas. Please follow traffic control signs and lane closures on Domenigoni Parkkway and Murrieta Hot Springs Road. Please expect delays and “DO NOT” drive over wet slurry material. Thank you for your patience and understanding.

Clinton Keith Phase 3 Weekly Update- May 2-6

The resurfacing on Leon Road from Jean Nicholas Road to Briggs Road and a major portion of Max Gilliss Boulevard from Leon Road to Winchester Road has been completed. The contractor applied a first coat of traffic stripe paint and is scheduled to apply a second coat of traffic stripe paint & pavement markings in the next two weeks. Please continue use caution while travelling through this area. New proposed Clinton Keith Road connecting Leon Road to Winchester Road (at Benton Road) is progressing well and still on schedule.