Clinton Keith Road - Weekly Status

The contractor is continuing the installation of steel reinforcement for the proposed bridge over French Valley Creek and importing soil for Clinton Keith Road from Leon Road to Winchester Road. In addition, the contractor has also begun the improvements along Winchester Road at Benton Road. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.

Carver Tract Weekly Update 10-31-22

We completed sidewalk construction and drainage improvements in the Carver Tract area. The contractor is installing pavement markings, doing minor work and clean up, then moving out soon. Please continue to use caution while travelling through the work zone.

Yvette Munozcarvertract
VIDEO UPDATE: Clinton Keith Road Phase 3 Oct. 24th - 28th

The contractor is continuing the installation of steel reinforcement for the proposed bridge over French Valley Creek and importing soil for Clinton Keith Road from Leon Road to Winchester Road. In addition, the contractor has also begun the improvements along Winchester Road at Benton Road. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.

Carver Tract Weekly Update

The contractor is working on the reconstruction of Luzon Street in the Carver Tract area. The contractor is scheduled to pave new asphalt on Luzon Street on Saturday, October 29, 2022. Please continue to use caution while travelling though the work zone. We appreciate your cooperation and understanding during the construction.

Yvette Munoz
Rainbow Canyon Road Resurfacing weekly update

The contractor is continuing the installation of roadside signs, minor curb painting, and other minor work. Please continue to use caution and expect minor delays with lane closures. Thank you for your understanding.

Yvette Munoz
Ramon Road Resurfacing and Trinity Circle Drainage Improvement - Weekly Update

The contractor is scheduled to replace asphalt pavement on Ramon Road from Varner Road to Monterey Road in the Thousand Palms area. Please observe traffic warning signs and expect delays. Thank you for your understanding.

Trinity Circle in the Bermuda Dunes: The contractor completed the majority of the work and is expected to complete on or ahead of schedule.

Steven Gray
Carver Tract Weekly Update

The contractor completed most of the underground work for the proposed Storm Water Underground Detention Basin on Luzon Street. Please continue to use caution while travelling though the work zone. We appreciate your cooperation and understanding during the construction.

Yvette Munozcarvertract
Soboba Resurfacing weekly update

Soboba Street Resurfacing from Stetson Avenue to Florida Avenue is considered complete. The contractor will perform some minor work and clean the project site next week. Please continue to use caution while travelling through.

 

Yvette Munozsoboba
Clinton Keith Road - Weekly Update Video

The construction for new proposed Clinton Keith Road from Leon Road to Winchester Road/Benton Road is progressing well. The contractor is continuing with the construction of a new bridge over French Valley Creek and importing material for the new roadway. Note: Briggs Road connecting Leon Road to Los Alamos Road is permanently CLOSED.

Lincoln Street Construction to begin October 17th

LINCOLN STREET CONSTRUCTION

To begin the week of October 17, 2022

The County of Riverside Transportation Department will rehabilitate Lincoln Street from Magnolia Avenue to Indiana Avenue. The project will last approximately 8 weeks.

Yvette Munozlincoln