The contractor is continuing the installation of forms and preparing for the placement of concrete to the proposed bridge over French Valley Creek, importing soil for Clinton Keith Road from Leon Road to Winchester Road. In addition, Murrieta Marketplace’s contractor is continuing the installation of sewer line (jack & bore) crossing under Winchester Road at Benton Road. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.
#HamnerAveProject
SUBSCRIBE for updates: Sign Up for Updates
TRAFFIC CONTROL
NB and SB Hamner Ave. at Citrus St.
Crews will work on the sidewalk, curbs and gutters on the shoulders at Citrus St., expect delays and traffic flagging when necessary.
Monday - Saturday
Nov. 14 - 19
7 a.m. - 5 p.m.
#RivCoTrans #NorcoCA #Eastvale #BuildingBridges #ConnectingCommunities #RivCo.
The contractor is continuing the installation and preparing for the placement of concrete to the proposed bridge over French Valley Creek, and importing soil for Clinton Keith Road from Leon Road to Winchester Road. In addition, Murrieta Marketplace’s contractor will start the installation of sewer line (jack & bore) crossing under Winchester Road at Benton Road. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.
We completed all concrete and asphalt pavement work on Ramon Road from Varner Road to Monterey Road in the Thousand Palms area. The contractor is working on the installation of traffic stripes, pavement markings, and other minor work. Please continue use caution while travelling through. Thank you for your cooperation.
Trinity Circle in the Bermuda Dunes: We are monitoring the drainage system.
Paving work is postponed until November 14 due to weather #LincolnStreet
#RivCoTrans
#ConnectingCommunities
@villegasms_ausd
@cityofriverside
@city_of_corona
Concrete work complete!
#LincolnSt.#RivCoTrans #ConnectingCommunities
Concrete work complete on the Lincoln Street project. Next up--
The contractor is continuing the installation of steel reinforcement for the proposed bridge over French Valley Creek and importing soil for Clinton Keith Road from Leon Road to Winchester Road. In addition, the contractor has also begun the improvements along Winchester Road at Benton Road. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.
We completed sidewalk construction and drainage improvements in the Carver Tract area. The contractor is installing pavement markings, doing minor work and clean up, then moving out soon. Please continue to use caution while travelling through the work zone.
We completed the reconstruction of Rainbow Canyon Road in the Temecula area. The contractor is cleaning and preparing to move out. Thank you for your patience and cooperation during construction.
#HamnerAveProject
TRAFFIC CONTROL
Monday, Oct. 31
7 a.m. - 5 p.m.
NB and SB Hamner Ave. at Citrus St.
Crews will work on the signal footing at Citrus St., please expect traffic flagging.
SUBSCRIBE for updates: https://www.hamneraveproject.com/updates/
#RivCoTrans thanks #NorcoCA and #Eastvale for your patience while crews continue #BuildingBridges and #ConnectingCommunities in #RivCo.
The contractor is continuing the installation of steel reinforcement for the proposed bridge over French Valley Creek and importing soil for Clinton Keith Road from Leon Road to Winchester Road. In addition, the contractor has also begun the improvements along Winchester Road at Benton Road. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.
The contractor is working on the reconstruction of Luzon Street in the Carver Tract area. The contractor is scheduled to pave new asphalt on Luzon Street on Saturday, October 29, 2022. Please continue to use caution while travelling though the work zone. We appreciate your cooperation and understanding during the construction.
The contractor is continuing the installation of roadside signs, minor curb painting, and other minor work. Please continue to use caution and expect minor delays with lane closures. Thank you for your understanding.
The contractor is scheduled to replace asphalt pavement on Ramon Road from Varner Road to Monterey Road in the Thousand Palms area. Please observe traffic warning signs and expect delays. Thank you for your understanding.
Trinity Circle in the Bermuda Dunes: The contractor completed the majority of the work and is expected to complete on or ahead of schedule.