Hamner Ave. Project - Week of November 13

#HamnerAveProject

 

Week of November 13

 

PROJECT PROGRESS

Construction continues on the bridge interior with a milestone concrete placement planned for late November, weather permitting. Crews completed curb and gutter concrete placement and will finish sidewalks from the bridge to Citrus Street.

 

REDUCE SPEED to 35 mph in the project area and watch for crews working on the shoulder at Detroit Street, Citrus Street and across the bridge. 

 

PEDESTRIAN ACCESS is available on the western side of Hamner Avenue from Schleisman Road to the southern crosswalk at Citrus Street. 

 

NO PEDESTRIAN ACCESS ACROSS THE BRIDGE in this phase of the project. 

 

PLEASE USE RTA @riversidetransit Route003, with stops at Taft Street and Hamner Avenue (northbound), and on Citrus Street west of Hamner Avenue (southbound). Please visit riversidetransit.com for information.

 

SUBSCRIBE at http://www.hamneraveproject.com/updates/ 

 

STAY CONNECTED on IG @hamneraveproject and on FB @Hamner Avenue Bridge and Widening Project. 

Video Block
Double-click here to add a video by URL or embed code. Learn more
Steven GrayHamner
Clinton Keith Road - Weekly Status


The proposed Clinton Keith Road from Leon Road to Winchester Road is continuing with shoulder, rock slope protection, drainage systems, concrete (curb, median, driveways, and sidewalk), and traffic signal systems. Murrieta Market Place replaced asphalt pavement and is scheduled to install pavement delineation on Benton Road from Temeku Street to Winchester Road. Thank you for your patience and understanding!



Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED (NO ACCESS).

Dist 4 & 5, Slurry Seal & Curb Ramps, Weekly status, Week ending 11/3/23

Field Work completed to date:

  • All curb ramps have been removed and replaced.

  • All traffic stripe and pavement markers have been removed in chip seal areas.

  • All crack seal has been completed in areas that get chip seal treatment.

Yvette Munozslurryseal
Slurry Seal, District 3, Weekly Update, Week ending 11/3/23

Field work completed to date:

·         Traffic control was set up daily per the approved traffic control plans for construction activities.

·         Finished reconstruction of ADA curb ramps. Reconstructed 36 curb ramps and repaired 5 with surface-mounted truncated domes and removed “lips” at the flowline.

·         Completed replacing asphalt pavement at various locations.

·         Finished applying herbicides on the pavement for weed abatement.

·         Started crack seal/crack fill and removing traffic stripe in the Hemet and Homeland areas.

 

Yvette Munozslurryseal
Sycamore Canyon Road Resurfacing - Weekly Status

We completed the reconstruction of Sycamore Canyon Road including pavement delineations and roadside signs from Central Avenue to Fair Isle Drive.

The contractor adjusted utilities (manholes) to new road grades. The contractor is scheduled to “Bump grind” (pavement smoothness) and fog seal the asphalt pavement on November 6th and 7th.

Please observe construction warning signs and follow traffic control personnel’s directions. We recommend using alternate routes if possible. Thank you for your patience and understanding.

Steven Graysycamore
Idyllwild Resurfacing - Weekly Status

We have completed about 95% of roadway improvements in the Idyllwild area. The contractor is continuing shoulder backing on Fern Valley Road and South Circle Drive. Please observe construction warning signs, follow flaggers’ directions, and expect delays while travelling through. We are trying our best to accommodate the traffic while facing challenges due to narrow road conditions. Thank you for your patience and understanding!

Steven GrayIdyllwild
Bridge Street at Ramona Expressway Traffic Signal - Weekly Status

Bridge Street at Ramona Expressway Traffic Signal - Weekly Status

The proposed traffic signal on Ramona Expressway at Bridge Street has resumed and scheduled to install Traffic Signal Poles and wiring this week. We are waiting for SCE to install service meters for the new proposed traffic signal & lighting system. Please observe construction warning signs. Thank you for your cooperation and understanding.

Steven Grayramona
Sycamore Canyon Project UPDATE

#SycamoreCanyonProject

 CONSTRUCTION CONTINUES

 

WEEK OF OCTOBER 30

 

NIGHTTIME WORK HOURS

8 p.m. to 5 a.m. Nightly

Monday - Sunday

 

Crews will be finishing and smoothing pavement throughout the project area. 

 

EXPECT TRAFFIC CONTROL

  • Sycamore Canyon Blvd. from Central Ave. to College Blvd.

  • Expect Delays.

  • Reduce speeds in the project area. 

  • Work is weather and field condition permitting.

 

Website: www.RCProjects.org/SycamoreCanyon

Hotline 877-277-5343

Steven Graysycamore
Hamner Ave Project - Week of October 23 ALERT

#HamnerAveProject

 

Week of October 23

 

TRAFFIC FLAGGING 

Thursday, Oct. 26

9 a.m. - 2 p.m.

Watch for crews on Hamner Avenue from Detroit to Citrus streets restriping pavement in the area. 

Add extra time for travel. 

 

REDUCE SPEED to 35 mph in the project area and watch for crews working on the shoulder at Detroit Street, Citrus Street and across the bridge. 

 

PEDESTRIAN ACCESS is available on the western side of Hamner Avenue from Schleisman Road to the southern crosswalk at Citrus Street. 

 

NO PEDESTRIAN ACCESS ACROSS THE BRIDGE in this phase of the project. 

 

PLEASE USE RTA @riversidetransit Route003, with stops at Taft Street and Hamner Avenue (northbound), and on Citrus Street west of Hamner Avenue (southbound). Please visit riversidetransit.com for information.

 

SUBSCRIBE at http://www.hamneraveproject.com/updates/ 

STAY CONNECTED on IG @hamneraveproject and on FB @Hamner Avenue Bridge and Widening Project. 

Steven GrayHamner
Slurry Seal & Curb Ramps FY 23-24 Dist. 1 & 2 SCHEDULE and MAP

Slurry Seal & Curb Ramps FY 23-24 Dist. 1 & 2 SCHEDULE and MAP

The contractor is scheduled to apply slurry seal coat to various streets in the Temescal Valley and El Cerritos areas (see attached schedule). We are continuing crack sealing in the Alessandro and Lake Elsinore areas. Please use caution while travelling through the work areas.

Please do not drive over wet slurry seal material. Thank you for your patience and understanding!

Steven Grayslurryseal
Bridge Street at Ramona Expressway - Weekly Status

The proposed traffic signal on Ramona Expressway at Bridge Street is suspended. We are waiting for SCE to inspect and to install service meters for the new proposed traffic signal & lighting system. We are anticipating it to be quick. Please observe construction warning signs. Thank you for your cooperation and understanding.

Steven Grayramona
IDYLLWILD Resurfacing Project 2023 UPDATE

#IDYLLWILD

Resurfacing Project 2023

Construction continues: Week of October 23

Hours: 7 a.m. - 6 p.m. Daily

Expect lane closures with traffic control in the Idyllwild community. Crews continue work to complete asphalt curb installation, backfilling, lane striping, sign installation, and landscaping work at several locations throughout

the project area.

Information: RCProjects.org/Idyllwild

Hotline: 877-277-5343

Steven GrayIdyllwild