Week of August 19 - 23 Dillon Rd, Bubbling Wells Resurfacing UPDATE

Week of August 19 - 23 Dillon Rd, Bubbling Wells Resurfacing UPDATE

We completed 95% of pavement replacement and other improvements on Dillon Road from Bubbling Wells Road to Palm Drive in the Community of Southeast Desert Hot Springs area. Next week, crews are scheduled to adjust manholes, paint pavement delineations, minor traffic signal work, and shoulder backing. Please use caution, observe construction warning signs, and follow directions from traffic control personnel. Thank you for your patience and understanding.

***Scheduled to start Bubbling Wells Road on August 28, 2024.

Week of August 19 - Mockingbird Canyon - Intermittent Lane Closures

Week of August 19: Intermittent lane closures planned through the traffic area.

Traffic Impacts
Plan for short lane closures throughout the project area with minor traffic delays. 
The contractor is completing driveway tie-ins, asphalt curbs and raising manholes.

Work Hours:
Weekdays 7 a.m. to 6 p.m.

Semana del 19 de agosto: Cierres de carriles intermitentes previstos en la zona de tráfico.

Impactos del tráfico
Planifique cierres de carriles cortos en toda el área del proyecto con retrasos menores en el tráfico. 
El contratista está completando los amarres de las entradas de vehículos, los bordillos de asfalto y levantando las alcantarillas.

Horas de trabajo:
Días laborables 7 a.m. a 6 p.m.

Yvette MunozMockingbird
Week of August 19 - 23 Mission Lakes, Little Morongo, Langlois Resurfacing Projects UPDATE

Week of August 19 - 23 Mission Lakes, Little Morongo, Langlois Resurfacing Projects UPDATE


We completed the improvements to Mission Lakes Blvd., Little Morongo Rd., and Langlois Rd. in the Desert Edge area. Crews are scheduled to complete shoulder work, some minor improvements, and clean the project sites. Please continue to use caution, observe construction warning signs, and follow directions from traffic control personnel. Thank you for your patience and understanding.

Jurupa Grade Separation Project Construction Alert: Week of August 19

Jurupa Grade Separation Project Construction Alert: Week of August 19


Construction Alert: Week of August 19

Lane closures on Van Buren Blvd. from Rutile St. to 52nd St.

Monday through Friday, Aug. 19-23

8:45 a.m. to 3 p.m.

Only one lane will be open in each direction.

EXPECT TRAFFIC DELAYS

Motorists can expect traffic delays throughout the week in the project area with the planned lane closures and new traffic pattern onto the newly opened bridge.

PLEASE REDUCE SPEED AND TRAVEL WITH CAUTION IN THE CONSTRUCTION AREA.

Stay up to date by visiting: www.jurupagradeseparation.com

Hotline: 800.679.9570

ALERTA DE CONSTRUCCIÓN: Semana de 19 de agosto

Cierres de carril sobre Van Buren Blvd. desde Rutile St. a 52nd St.


Lunes a Viernes, 19-23, de agosto

8:45 a.m. a 3 p.m.


ANTICIPÉ RETRASOS EN EL TRÁFICO

Automovilistas pueden anticipar retrasos en el tráfico durante la semana en el área de el proyecto con cierres de carriles y un tramo nuevo de tráfico hacia el puente que se acaba de abrir.


!! FAVOR DE REDUCIR SU VELOCIDAD EN EL ÁREA DE CONSTRUCCIÓN Y VIAJE CON PRECAUCIÓN !!


Manténgase al margen visitando

www.jurupagradeseparation.com

Línea directa: 800.679.9570

Steven GrayJurupaGrade
Construction Alert: Nighttime Road Closure - Hamner Ave Bridge

NIGHTTIME ROAD CLOSURE

Monday through Tuesday | Aug. 19, 20
10 p.m. to 5 a.m. 

Full road closure on Hamner Ave. from Detroit St. to Citrus St., use the posted detour to River Rd.

Please plan for delays and use alternate routes.

Hotline: 877.278.7606

Visit our project website at hamneraveproject.com.

#HamnerAve #Norco 

Yvette MunozHamner
Construction Alert: Clinton Keith Road

!ALERT!


Clinton Keith Road: Bridge Deck Grooving


Crews are scheduled to work on Clinton Keith Road at French Valley Bridge between Winchester Road and Leon Road on Wednesday, 8/14/24 from 10:00PM to 5:00AM. Please observe construction warning signs and drive slow through work area. Thank you for your patience and understanding.

Steven Grayclintonkeith
Week of August 12-16 - Dillon and Bubbling Wells Resurfacing UPDATE

We completed the reconstruction of concrete cross-gutter and curb & gutter on Dillon Road and Bubbling Wells Road in the Community of Southeast Desert Hot Springs area. Next week, crews are scheduled to remove & replace of existing asphalt pavement on Dillon Road (from Palm Drive to Mountain View Road). Please use caution, observe construction warning signs, and follow directions from traffic control personnel. Thank you for your patience and understanding.





Week of August 12-16 - Mission, Little Morongo, Langlois UPDATE

We completed the replacement of asphalt pavement to Mission Lakes Blvd, Little Morongo Rd, and Langlois Rd. in the Desert Edge area. Crews are scheduled to work on other improvements along the shoulder, traffic stripe, pavement markings, and roadside signs. Please continue to use caution, observe construction warning signs, and follow directions from traffic control personnel. Thank you for your patience and understanding.

Mockingbird Canyon Road Update | Week of August 12th

Week of August 12 

Construction Alert: Week of August 12 

Mockingbird Canyon Road | Week of August 12 

This week, the contractor will be working on driveway tie ins in various locations on Mockingbird Canyon Rd. with smaller lane closures in place. 

Flaggers will assist motorists through the closure. Please drive with caution and reduce speed while driving in the construction zone.  

Work Hours 

7 a.m. to 6 p.m. 

 

Alerta de construccion: Semana de 12 de agosto 

Esta semana, el contratista trabajará en los vínculos de las entradas de vehículos en varios lugares de Mockingbird Canyon Rd. con cierres de carriles más pequeños.  

Los banderados ayudarán a los automovilistas durante el cierre. Conduzca con precaución y reduzca la velocidad mientras conduce en la zona de construcción. 

Horas de trabajo 

7 a.m. a 6 p.m. 

Stay Connected | Mantengase Informado  

Rcprojects.org/mockingbird

Hotline: 877-277-5343 

#MockingbirdCanyonRoadResurfacingProject #Woodcrest  

Steven GrayMockingbird
48th Avenue Widening and Resurfacing - Weekly Status

We continue with the reconstruction and widening of 48th Avenue from Van Buren Blvd. to Grapefruit Blvd. in the Carver Tract Community and City of Indio/Coachella area. Crews are on schedule with the roadway reconstruction. Starting August 12th, traffic will be changed to outside lanes. Please use caution, observe construction warning signs, and follow directions from traffic control personnel. Thank you for your patience and understanding.

Steven Gray48th Ave
HAMNER AVE CONSTRUCTION ALERT - FULL ROAD CLOSURE 

FULL ROAD CLOSURE 

Thursday and Friday nights| Aug. 8, 9 | 10 p.m. to 5 a.m. 

Full road closure on Hamner Ave. from Detroit St. to Citrus St., use posted detour to River Rd. 

Please plan for delays and use alternate routes. 

Hotline: 877.278.7606 

Visit our project website at hamneraveproject.com for the latest updates. 

#HamnerAve #Norco 

@CiyofEastvale @RivcoTrans @CityofNorco 

Steven GrayHamner
Week of August 5-9 Dillon and Bubbling Wells Resurfacing UPDATE

We completed the reconstruction of concrete cross-gutter and curb & gutter on Dillon Road and Bubbling Wells Road in the Community of Southeast Desert Hot Springs area. Crews are preparing for removal & replacement of existing asphalt on Dillon Road (from Palm Drive to Mountain View Road) and Bubbling Wells Road (from 20th Avenue and Dillon Road). We anticipate completing this project in early October 2024. Please use caution, observe construction warning signs, and follow directions from traffic control personnel. Thank you for your patience and understanding.

Mockingbird Canyon Road Resurfacing | Week of August 5

CONSTRCUTION ALERT: Monday-Saturday, Aug. 5-10, Mockingbird Canyon Road project

This week, crews will place the final layer of asphalt on Mockingbird Canyon Rd. between Markham St. and Van Buren Blvd.

Expect lane closures with one lane open for traffic in both directions and possible delays up to 10 minutes. Flaggers will assist motorists through the closure.

Please drive with caution and reduce speed while driving in the construction zone.

Work Hours

7 a.m. to 6 p.m.

ALERTA DE CONSTRUCCION: Lunes-Sabado, 5-10 de agosto, Proyecto Mockingbird Canyon Road

Esta semana, las cuadrillas colocarán la capa final de asfalto en Mockingbird Canyon Rd. entre Markham St. y Van Buren Blvd.

Anticipe cierres de carril en ambas direcciones y retrasos de 10 minutos. Los banderadores ayudarán a los automovilistas durante el cierre.

Conduzca con precaución y reduzca la velocidad mientras conduce en la zona de construcción.

Horario

7 a.m. a 6 p.m.

Stay Connected | Mantengase Informado

Rcproject.org/mockingbird

Hotline: 877-277-5343

#MockingbirdCanyonRoadResurfacingProject #Woodcrest


Steven GrayMockingbird
Week of August 5-9 - Mission, Little Morongo, Langlois UPDATE

We completed the replacement of asphalt pavement to Mission Lakes Blvd., Little Morongo Rd., and Langlois Rd. in the Desert Edge area . Crews are scheduled to work on shoulder and utility adjustment on the roadway. Please continue to use caution, observe construction warning signs, and follow directions from traffic control personnel. Thank you for your patience and understanding.