Clark St Resurfacing and Sidewalk - Weekly Status

Crews have begun road improvements on Clark St from Martin St to Nandina Ave in the Mead Valley Community. Crews will be closing small segments of Clark St and detouring traffic between 7:00 AM and 6:00 PM in order to prepare for the construction of concrete curb and gutter. Please observe construction detour and warning signs, use caution, and follow traffic control staff’s directions. Thank you for your patience and understanding.

Steven Gray
Gilman Springs - Update

Project Update--> Week of January 27, 2025  

Crews are making progress on Gilman Springs Road construction south of Bridge Street and are on schedule to open the road in early February.  

Work includes shoulder widening, wildlife fencing, drainage work, and installing a concrete center median.  

Gilman Springs Road is open north of Bridge Street; motorists may detour around the closure using Ramona Expressway and Bridge Street.   

The Riverside County Transportation Department is monitoring detour conditions and is adjusting the traffic signal accordingly at Bridge St. and Ramona Expressway. 

Please drive with caution, avoid distracted driving, and plan for longer wait times in this area during construction.   

Due to high wind events in the area, power outages are occurring to help prevent wildfires and may shut off traffic signals. All motorists are required to treat an intersection with an inoperable traffic signal as an all-way stop and may proceed with caution when safe to do so per California Vehicle Code Section 21800 (d) (1). 

 

Actualización del proyecto--> Semana del 20 de enero de 2025  

Los equipos están avanzando en la construcción de Gilman Springs Road al sur de Bridge Street y están a tiempo de abrir la carretera a principios de febrero.  

El trabajo incluye la ampliación de los arcenes, la cerca para la vida silvestre, el trabajo de drenaje y la instalación de una mediana central de hormigón.   

Gilman Springs Road está abierta al norte de Bridge Street; los automovilistas pueden desviarse para evitar el cierre utilizando Ramona Expressway y Bridge Street. 

El Departamento de Transporte del Condado de Riverside está monitoreando las condiciones de los desvíos y está ajustando la señal de tránsito en consecuencia en Bridge St. y Ramona Expressway.   

Conduzca con precaución, evite conducir distraído y planifique tiempos de espera más prolongados en esta área durante la construcción.    

Debido a los fuertes vientos en el área, se están produciendo cortes de energía para ayudar a prevenir incendios forestales y es posible que se corten las señales de tránsito. Todos los conductores deben tratar una intersección con un semáforo inoperable como una parada total y pueden proceder con precaución cuando sea seguro hacerlo según la Sección 21800 (d) (1) del Código de Vehículos de California. 

Please visit the project website at www.rcprojects.org/gilman for updates. 

Hotline: 877.277.5343  

Visite el sitio web del proyecto en www.rcprojects.org/gilman para obtener actualizaciones.  

Línea directa: 877.277.5343 

Yvette Munozgilmanphase6
Slurry Seal FY24-25 District 4,5 - Weekly Status

- The slurry crew is working in Cabazon area.

- The striping crew is also working in Cabazon area.

- Due to the weather, some of the work was delayed and schedule to be done by next week.

- Extra work, install additional channelizers on Yucca /lane in Bermuda Dunes, will be done soon.

Steven Grayslurryseal
Oleander Avenue Sidewalk - Weekly Status

We are continuing with the road widening and new proposed sidewalk project on Oleander Avenue from Haines Street to Clark Street in the Community of Mead Valley. The project is scheduled to complete in February 2025. Crews are working on the construction of new concrete sidewalk, driveways, cross-gutter, and roadway excavation. Please observe construction warning signs, use caution, and follow traffic control staff’s directions. Thank you for your patience and understanding.

Steven GrayOleander 2025
Weekly Update: Indiana Ave Resurfacing Grant Street & Harlow Ave Resurfacing

Week Ending: 01/17/2025

Pavement reconstruction and concrete improvements on Grant Street and Harlow Avenue in the Home Gardens area have been completed. The contractor is continuing concrete improvements on Indiana Avenue, from Grant Street to Hillview Drive.

Please observe all construction warning signs, use caution, and follow the directions of traffic control staff.

Thank you for your patience and understanding.

Yvette Munoz
CONSTRUCTION ALERT: Road and lane closures planned: Week of Jan. 20, 2025

CONSTRUCTION ALERT: Road and lane closures planned: Week of Jan. 20, 2025

Reminder: 2-Week ROAD CLOSURE planned at Pedley and Jurupa roads starting Jan. 20.

Inside lane closures planned on Van Buren Blvd. On Jan. 21 and 22.

TRAFFIC IMPACTS

Road Closure

Mon., Jan. 20, at 5 a.m. through

Fri., Jan. 31, at 6 p.m.

The intersection at Pedley and Jurupa roads will be closed to through traffic. Please use the posted detour 54th Street to Agate Street.

Inside Lane Closures on Van Buren Blvd.

Mon., Jan. 21, and Tues., Jan. 22

8 a.m. to 1 p.m.

Expect the inside northbound and southbound lanes on Van Buren Blvd. to be closed. Please reduce speed through the construction zone.

This information may change due to weather or field conditions.

--------------------------------------------------------------------------------------

ALERTA DE CONSTRUCCIÓN: Cierres de caminos y carriles planificados: Semana del 20 de enero de 2025

Recordatorio: CIERRE DE CARRETERAS planificado durante 2 semanas en las calles Pedley y Jurupa a partir del 20 de enero. Cierres de carriles interiores planificados en Van Buren Blvd. el 21 y 22 de enero.

IMPACTOS EN EL TRÁFICO

Cierre de carretera

Lunes 20 de enero, a las 5 a.m. hasta

Viernes 31 de enero a las 6 p.m.

La intersección de las calles Pedley y Jurupa estará cerrada al tráfico de tránsito. Utilice el desvío indicado de 54th Street a Agate Street.

Cierres de carriles interiores en Van Buren Blvd.

Lunes 21 de enero y martes 22 de enero

de 8 a.m. a 1 p.m.

Se espera que los carriles interiores en dirección norte y sur de Van Buren Blvd. estén cerrados. Reduzca la velocidad en la zona de construcción.

Esta información puede cambiar debido al clima o las condiciones del campo.

Hotline: 800.679.9570

Linea Directa: 800.679.9570

For more information visit: www.jurupagradeseparation.com

Para mas informacion visite: www.jurupagradeseparation.com

Steven GrayJurupaGrade
El Cerrito Area Resurfacing - Weekly Status

We completed all concrete and roadway improvements to various streets in the El Cerrito area of County of Riverside. Crews are working on pavement markings and cleaning up the project site. Thank you for your patience and understanding.

Steven Gray
Cornell Street Resurfacing - Weekly Status

We completed pavement reconstruction on Cornell Street from Florida Avenue to Crest Drive Avenue in the East Hemet area. Crews are continuing with minor repairs and cleaning the project site. Please observe construction warning signs, use caution, and follow traffic control staff’s directions. Thank you for your patience and understanding.

Steven GrayCornell 2025
Gilman Springs Road will be CLOSED to through traffic SOUTH of Bridge St. beginning Saturday, Jan. 4, at 8 p.m., weather permitting  

PLAN AHEAD: Gilman Springs Road will be CLOSED to through traffic SOUTH of Bridge St.   

beginning Saturday, Jan. 4, at 8 p.m., weather permitting  

  

TRAFFIC IMPACTS  

·         Gilman Springs Road will be closed to through traffic SOUTH of Bridge St. for approximately 1 mile. Business and resident access is open.   

·         Gilman Springs Road is open to traffic from Bridge St. to SR 60.  

·         Motorists may detour onto Ramona Expressway to Bridge St. to access Gilman Springs Road north of Bridge St.   

·         Please plan for delays and use alternate routes.   

 

Work schedules may change due to weather or field conditions.  

Crews may work 24 hours per day, 7 days a week.  

--------------------------------------------  

PLANNE CON ANTICIPACION: Gilman Springs Road estará CERRADA al tráfico al SUR de Bridge St. a partir del sábado 4 de enero a las 8 p.m., si el clima lo permite   

   

IMPACTOS DEL TRÁFICO   

   

·         Gilman Springs Road estará cerrada al tráfico al SUR de Bridge St. durante aproximadamente 1 milla. El acceso para empresas y residentes está abierto. 

   

·         Gilman Springs Road está abierta al tráfico desde Bridge St. hasta SR 60.   

   

·         Los automovilistas pueden desviarse hacia Ramona Expressway hacia Bridge St. para acceder a Gilman Springs Road al norte de Bridge St.    

   

·         Planifique los retrasos y utilice rutas alternativas.    

   

Los horarios de trabajo pueden cambiar debido al clima o las condiciones del campo. Las cuadrillas pueden trabajar las 24 horas del día, los 7 días de la semana.  

  

Hotline: 877.277.5343   

Linea Directa: 877.277.5343   

    

Website: www.rcproject.org/gilman   

Sitio web: www.rcproject.org/gilman  

Yvette Munozgilmanphase6
REMINDER: Gilman Springs Road will be CLOSED beginning Saturday, Jan. 4, at 8PM

REMINDER: Gilman Springs Road will be CLOSED to through traffic SOUTH of Bridge St.   

beginning Saturday, Jan. 4, at 8 p.m., weather permitting  

  

TRAFFIC IMPACTS  

·        Gilman Springs Road will be closed to through traffic SOUTH of Bridge St. for approximately 1 mile. Business and resident access is open.   

·        Gilman Springs Road is open to traffic from Bridge St. to SR 60.  

·        Motorists may detour onto Ramona Expressway to Bridge St. to access Gilman Springs Road north of Bridge St.   

·        Please plan for delays and use alternate routes.   

 

Work schedules may change due to weather or field conditions.  

Crews may work 24 hours per day, 7 days a week.  

--------------------------------------------  

RECORDATORIO: Gilman Springs Road estará CERRADA al tráfico al SUR de Bridge St. a partir del sábado 4 de enero a las 8 p.m., si el clima lo permite   

   

IMPACTOS DEL TRÁFICO   

   

·        Gilman Springs Road estará cerrada al tráfico al SUR de Bridge St. durante aproximadamente 1 milla. El acceso para empresas y residentes está abierto. 

   

·        Gilman Springs Road está abierta al tráfico desde Bridge St. hasta SR 60.   

   

·        Los automovilistas pueden desviarse hacia Ramona Expressway hacia Bridge St. para acceder a Gilman Springs Road al norte de Bridge St.    

   

·        Planifique los retrasos y utilice rutas alternativas.    

   

Los horarios de trabajo pueden cambiar debido al clima o las condiciones del campo. Las cuadrillas pueden trabajar las 24 horas del día, los 7 días de la semana.  

  

Hotline: 877.277.5343   

Linea Directa: 877.277.5343   

    

Website: www.rcproject.org/gilman   

Sitio web: www.rcproject.org/gilman   

Construction Update: Cornell Street – East Hemet

Construction Update: Cornell Street – East Hemet

We have completed the concrete improvements and replaced the asphalt pavement on Cornell Street from Florida Avenue to Crest Drive Avenue in the Community of East Hemet.

The contractor is currently working on the asphalt driveway tie-ins and cleaning the project site. Traffic striping is scheduled for the second week of January 2025.

Please observe all construction warning signs, use caution, and follow the directions of the traffic control staff to ensure safety.

We appreciate your patience and understanding as we complete this project.

Thank you!

Yvette Munoz