The contractor is continuing the preparation for the placement of concrete to proposed bridge over French Valley Creek, importing soil for the proposed Clinton Keith Road from Leon Road to Winchester Road. In addition, Murrieta Marketplace’s contractor is continuing the installation of sewer line crossing under Winchester Road at Benton Road. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.
#HamnerAveProject
EXPANDED WORK HOURS
Saturday | Dec. 3 & 10 | 6 a.m. - 3:30 p.m.
Saturday work planned on the western span of the new bridge and on the bridge approach at the south end.
NEW TRAFFIC PATTERN COMING SOON
Crews are working toward opening the western span of the new bridge and shifting both north and southbound traffic onto it in mid-December. Multiple tasks must be completed with acceptable weather conditions to meet this schedule or the operation will be postponed until mid-January.
CHECK OUT the project website and social media for updates and details the week of Dec. 5.
SUBSCRIBE for updates: https://www.hamneraveproject.com/updates/
IG:@hamneraveproject
FB: Hamner Avenue Bridge and Widening Project
#RivCoTrans
Thank You-->#NorcoCA #Eastvale
Crews continue #BuildingBridges #ConnectingCommunities #RivCo
The contractor is continuing the preparation for the placement of concrete to proposed bridge over French Valley Creek, importing soil for the proposed Clinton Keith Road from Leon Road to Winchester Road. In addition, Murrieta Marketplace’s contractor is continuing the installation of sewer line crossing under Winchester Road at Benton Road. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.
#JurupaGradeSeparation
Check out our latest peek->BEHIND THE K-RAIL
Crews continue to work on the Van Buren Blvd. bridge and the Jurupa Rd. underpass support systems. #ConnectingJurupaValley #RivCoTrans #ConnectingCommunities #BuildingBridges
SUBSCRIBE:
UPDATES http://www.JurupaGradeSeparation.com
FOLLOW & SHARE:
on Fb @Jurupa Grade Separation Project
SHOP local #ShopLocalJurupaValley #ShopJV #ShopJurupaValley #JurupaValley
BUSINESS DIRECTORY:
https://www.jurupagradeseparation.com/business-directory/
BUSINESS ACCESS REMAINS OPEN at ALL Felspar St. and Jurupa Rd business plaza's.
#HamnerAveProject
TRAFFIC CONTROL
Tuesday & Wednesday | Nov. 22 & Nov. 23 | 7 a.m. - 5 p.m.
NB and SB Hamner Ave. from Detroit Street to Citrus Street.
Crews will pave on the north and south side of the project. Expect delays and traffic flagging.
NEW TRAFFIC PATTERN COMING SOON
Once paving operations are complete on the north and south side bridge approaches and the road widening sections, crews will continue to work on the final touches of the western bridge span. The western bridge span will open to motorists and traffic will switch tentatively in mid-December. Check the project website and social media for details. The existing Hamner Avenue Bridge will be retired, and crews will begin the construction of the eastern bridge span. The project is tentatively scheduled to be complete by the summer of 2024.
SUBSCRIBE for updates: Sign Up for Updates
#RivCoTrans #NorcoCA #Eastvale #BuildingBridges #ConnectingCommunities #RivCo.
The contractor is continuing the installation of forms and preparing for the placement of concrete to the proposed bridge over French Valley Creek, importing soil for Clinton Keith Road from Leon Road to Winchester Road. In addition, Murrieta Marketplace’s contractor is continuing the installation of sewer line (jack & bore) crossing under Winchester Road at Benton Road. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.
#HamnerAveProject
SUBSCRIBE for updates: Sign Up for Updates
TRAFFIC CONTROL
NB and SB Hamner Ave. at Citrus St.
Crews will work on the sidewalk, curbs and gutters on the shoulders at Citrus St., expect delays and traffic flagging when necessary.
Monday - Saturday
Nov. 14 - 19
7 a.m. - 5 p.m.
#RivCoTrans #NorcoCA #Eastvale #BuildingBridges #ConnectingCommunities #RivCo.
The contractor is continuing the installation and preparing for the placement of concrete to the proposed bridge over French Valley Creek, and importing soil for Clinton Keith Road from Leon Road to Winchester Road. In addition, Murrieta Marketplace’s contractor will start the installation of sewer line (jack & bore) crossing under Winchester Road at Benton Road. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.
We completed all concrete and asphalt pavement work on Ramon Road from Varner Road to Monterey Road in the Thousand Palms area. The contractor is working on the installation of traffic stripes, pavement markings, and other minor work. Please continue use caution while travelling through. Thank you for your cooperation.
Trinity Circle in the Bermuda Dunes: We are monitoring the drainage system.
Paving work is postponed until November 14 due to weather #LincolnStreet
#RivCoTrans
#ConnectingCommunities
@villegasms_ausd
@cityofriverside
@city_of_corona
Concrete work complete!
#LincolnSt.#RivCoTrans #ConnectingCommunities
Concrete work complete on the Lincoln Street project. Next up--
The contractor is continuing the installation of steel reinforcement for the proposed bridge over French Valley Creek and importing soil for Clinton Keith Road from Leon Road to Winchester Road. In addition, the contractor has also begun the improvements along Winchester Road at Benton Road. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.
We completed sidewalk construction and drainage improvements in the Carver Tract area. The contractor is installing pavement markings, doing minor work and clean up, then moving out soon. Please continue to use caution while travelling through the work zone.
We completed the reconstruction of Rainbow Canyon Road in the Temecula area. The contractor is cleaning and preparing to move out. Thank you for your patience and cooperation during construction.