The contractor completed slurry seal application, including all pavement delineations, to Desert Hot Springs area, Airport Blvd. (Thermal area), and Cabazon area. The project is temporarily suspended until May 14, 2023 due to low temperature at night for Reche Vista Drive, Reche Canyon Road and Gilman Hot Springs Road. Please visit our Transportation website for more information regarding Slurry Seal applications. www.rcprojects.org/slurryseal
Lake Elsinore area: Completed application of new slurry seal to Audelo Street, Patrick Court, and Monty Court on Saturday April 22, 2023. Scheduled to apply new slurry seal to neighborhood streets.
Coronita area: Continue to crack seal existing asphalt pavement on various streets and begin slurry application. Slurry Seal application for Paseo Grande Road was scheduled on Saturday, April 22, 2023 (partial completed and to be scheduled to complete to accommodate school traffic).
Home Gardens area: Completed replacement of concrete curb ramps.
Woodcrest area: Repair & prepare existing asphalt pavement for slurry seal application.
Please follows construction warning signs and DO NOT park vehicles on street with posted “NO PARKING” signs. Thank you for your cooperation and understanding.
Please visit our Transportation website for more information regarding Slurry Seal applications. www.rcprojects.org/slurryseal
#EastHemet
#StetsonAveProject
#GirardStProject
RAMONA BOWL EVENT:
From E. Florida Ave. PLEASE USE San Jacinto St. to Stetson Ave. to Girard St.
OR Stetson Ave. to Girard St.
Crews continue to work on pavement improvements in the area.
Monday - Friday and possibly Saturday 7 a.m. - 6 p.m.
The contractor completed new proposed concrete median for Ramona Expressway Median from Rider Street (3/4 Miles easterly) towards Warren Road in the Community of Nuevo, Lakeview, and Gilman Springs. Please use caution due to new raised concrete median and obey traffic control personnel while travelling through the area. Thank you for your patience and understanding!
#RamonaExpresswayMedianProject
THANKS for your patience during this roadway construction project on Ramona Expressway.
#RivCoTrans installed a 22-inch-wide by 8-inch-high concrete center median on 8.5 miles of #RamonaExpressway from approximately ¾-of-a-mile east of Rider Street on the west end, to Warren Road on the east end, to improve public safety.
PLEASE continue to #DRIVEwithCARE #RamonaExpressway.
NEXT UP: Bridge Street traffic signal installation, coming this summer.
Construction Alert
The Flood Control District will be repairing stormdrain damaged from the recent storms starting next week.
Repairs on the East Ontario Ave Stormdrain Sinkhole can be expected:
April 24, 2023, through May 8, 2023
Monday through Friday, 7 am – 7 pm
Between State Street and Grovewood Drive
For questions, contact 951-955-1278
________________________________
Alerta de Construcción
El Distrito de Control de Inundaciones estará reparando alcantarilla dañada durante las recientes tormentas empezando la próxima semana.
Reparaciones en la alcantarilla de East Ontario Ave se pueden esperar:
24 de abril de 2023 hasta el 8 de mayo de 2023
Lunes a Viernes 7 am - 7 pm
Entre State Street y Grovewood Drive
Para cualquier pregunta, contacte 951-955-1278
#EastHemet
Check out the latest...
for the #StetsonAveProject and the #GirardStProject.
Crews continue to work on pavement improvements, Monday - Friday and possible Saturdays 7 a.m. - 4 p.m.
Slurry Seal FY 22-23 Dist. 1 & 2
We completed concrete curb ramps in the Lake Elsinore area and Coronita areas. Upcoming work schedule as follows:
Lake Elsinore area: Pavement repairs to various streets and scheduled for the application of new slurry seal to Audelo Street, Patrick Court, and Monty Court on Saturday April 22, 2023.
Coronita area: Crack seal to existing asphalt pavement to various streets. Slurry Seal application for Paseo Grande Road is scheduled on Saturday, April 22, 2023.
Home Gardens area: Replace concrete curb ramps.
Please follow construction warning signs and DO NOT park vehicles on street with posted “NO PARKING” signs. Thank you for your cooperation and understanding.
Please visit our Transportation website for more information regarding Slurry Seal applications. Slurry Seal — Riverside County Projects (rcprojects.org)
Slurry Seal FY 22-23 Dist 4 & 5
The contractor completed slurry seal application to Desert Hot Springs area & Airport Blvd. (Thermal area), and Cabazon area. Scheduled to complete all traffic stripe and pavement markings on Saturday, April 15, 2023. The project is temporary suspended until May 14, 2023 due to low temperature at night for Reche Canyon Road and Gilman Hot Springs Road.
Please visit our Transportation website for more information regarding Slurry Seal applications. Slurry Seal — Riverside County Projects (rcprojects.org)
Nighttime work is planned for Friday, April 14, 8PM-5AM. Expect lane closures with pilot car escorts.
The contractor is continuing with the removal & replacement of the existing concrete cross-gutter, spandrels, curb ramps, and asphalt pavement on Girard Street improvements from Stetson Avenue towards Florida Avenue in the East Hemet area. There will be road closures to through traffic due to wide cross-gutter replacement work and pavement reconstruction. Please use caution, observe construction warning signs, follow detour signs, and expect delays while travelling through the area. Thank you for your understanding and patience.
The contractor is continuing with replacing the existing asphalt pavement on Stetson Avenue from Santa Fe Street to Hemet Street in the East Hemet area. The construction progress is moving as planned. Please use caution, observe construction warning signs, and expect delays while travelling through the area. Thank you for your understanding and patience.
The contractor resumed the construction of new proposed drain and slope/gully on Grant Avenue in the Valle Vista Community. The project is moving along well. There is no major impact to traffic. Please be aware of truck traffic on Grant Avenue south of Florida Avenue during normal working hours. Thank you.
Clinton Keith Road Extension Project, Construction Notice, Week of April 10-14, 2023. Please visit www.clintonkeithphase3.org for more project information.
#RamonaExpresswayMedianProject
CONSTRUCTION UPDATE:
#RamonaExpressway #RamonaMedian
Fri. and Sat. nighttime work planned
April 7, 8 | 8 p.m. to 5 a.m.
Expect nighttime lane closures with pilot car escorts at both east and west ends of the project.
Plan for delays. Speed limit is 35 MPH in project area. #RivCoTrans
Slurry Seal FY 22-23, District 4 & 5 Weekly Status, week ending March 30, 2023 - The contractor is actively applying slurry seal to the Desert Hot Springs area and is scheduled to install pavement delineations this upcoming week to complete the slurry seal areas. We are also working on Crack Seal and pavement preparation in the Thermal area. Please visit our Transportation website for more information regarding Slurry Seal applications.