The proposed Clinton Keith Road from Leon Road to Winchester Road is continuing with drainage systems, concrete (curb & median), soil stabilization, and traffic signal systems. Thank you for your patience and understanding!
Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED (NO ACCESS).
Week of November 20
TRAFFIC IMPACTS
FELSPAR STREET
MONDAY - WEDNESDAY
6 a.m. - 5 p.m.
Lane closures
Traffic flaggers to assist motorists through the construction zone with parking restrictions.
BUSINESS ACCESS REMAINS OPEN
LUNES a MIERCOLES
6 a.m. - 5 p.m.
Cierres de carriles
Señalizadores de tráfico para ayudar al tráfico a través de la zona de construcción, restricciones de estacionamiento
EL ACCESO EMPRESARIAL PERMANECE ABIERTO
Jurupa Road
Felspar Street
Pedley Road
BUSINESS ACCESS REMAINS OPEN
>USE JURUPA RD. DETOURS<
Van Buren Blvd. to Rutile St. to Galena St. to Felspar St.
OR Van Buren Blvd. to Limonite Ave. to Pedley Rd. to Jurupa Rd.
@donut_tyme_jv -->DONUTS and MORE!
@drtoothdentalandortho
@jdmissionsteakhousejv
@pizzakingjurupa
@plazaliquor1 >>Lucky Lottery Location
@ southridgecycling
Jurupa Road & Rutile Street
BUSINESS ACCESS REMAINS OPEN
>USE JURUPA RD. DETOURS<
Van Buren Blvd. to Jurupa Connector Rd.
OR use Rutile St.
#HamnerAveProject
PROJECT PROGRESS
Crews continue to work on eastern span bridge interior construction with a concrete placement scheduled for Dec. 1. Construction throughout the project area continues.
REDUCE SPEED to 35 mph in the project area, watch for crews working on the shoulder from Detroit Street to Citrus Street and along the length of the bridge.
PEDESTRIAN ACCESS available on the western side of Hamner Avenue from Schleisman Road to the southern crosswalk at Citrus Street.
NO PEDESTRIAN ACCESS ACROSS THE BRIDGE in this phase of the project.
PLEASE USE RTA @riversidetransit Route003
Bus stops at
Taft Street and Hamner Avenue (northbound)
AND
Citrus Street west of Hamner Avenue (southbound)
Please visit riversidetransit.com for route specific information.
SUBSCRIBE at http://www.hamneraveproject.com/updates/
STAY CONNECTED on IG @hamneraveproject and on FB @Hamner Avenue Bridge and Widening Project
La Cresta Area Striping Removal Schedule and Map
#HamnerAveProject
Week of November 13
PROJECT PROGRESS
Construction continues on the bridge interior with a milestone concrete placement planned for late November, weather permitting. Crews completed curb and gutter concrete placement and will finish sidewalks from the bridge to Citrus Street.
REDUCE SPEED to 35 mph in the project area and watch for crews working on the shoulder at Detroit Street, Citrus Street and across the bridge.
PEDESTRIAN ACCESS is available on the western side of Hamner Avenue from Schleisman Road to the southern crosswalk at Citrus Street.
NO PEDESTRIAN ACCESS ACROSS THE BRIDGE in this phase of the project.
PLEASE USE RTA @riversidetransit Route003, with stops at Taft Street and Hamner Avenue (northbound), and on Citrus Street west of Hamner Avenue (southbound). Please visit riversidetransit.com for information.
SUBSCRIBE at http://www.hamneraveproject.com/updates/
STAY CONNECTED on IG @hamneraveproject and on FB @Hamner Avenue Bridge and Widening Project.
COMPLETED: The Riverside County Transportation Department completed the Sycamore Canyon Roadway Resurfacing Project. #RivCoTrans
The proposed Clinton Keith Road from Leon Road to Winchester Road is continuing with shoulder, rock slope protection, drainage systems, concrete (curb, median, driveways, and sidewalk), and traffic signal systems. Murrieta Market Place replaced asphalt pavement and is scheduled to install pavement delineation on Benton Road from Temeku Street to Winchester Road. Thank you for your patience and understanding!
Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED (NO ACCESS).
Field Work completed to date:
All curb ramps have been removed and replaced.
All traffic stripe and pavement markers have been removed in chip seal areas.
All crack seal has been completed in areas that get chip seal treatment.
Chip Seal, Weekly Schedule, Week of November 6, 2023
Field work completed to date:
· Traffic control was set up daily per the approved traffic control plans for construction activities.
· Finished reconstruction of ADA curb ramps. Reconstructed 36 curb ramps and repaired 5 with surface-mounted truncated domes and removed “lips” at the flowline.
· Completed replacing asphalt pavement at various locations.
· Finished applying herbicides on the pavement for weed abatement.
· Started crack seal/crack fill and removing traffic stripe in the Hemet and Homeland areas.
We completed the reconstruction of Sycamore Canyon Road including pavement delineations and roadside signs from Central Avenue to Fair Isle Drive.
The contractor adjusted utilities (manholes) to new road grades. The contractor is scheduled to “Bump grind” (pavement smoothness) and fog seal the asphalt pavement on November 6th and 7th.
Please observe construction warning signs and follow traffic control personnel’s directions. We recommend using alternate routes if possible. Thank you for your patience and understanding.
We have completed about 95% of roadway improvements in the Idyllwild area. The contractor is continuing shoulder backing on Fern Valley Road and South Circle Drive. Please observe construction warning signs, follow flaggers’ directions, and expect delays while travelling through. We are trying our best to accommodate the traffic while facing challenges due to narrow road conditions. Thank you for your patience and understanding!
Bridge Street at Ramona Expressway Traffic Signal - Weekly Status
The proposed traffic signal on Ramona Expressway at Bridge Street has resumed and scheduled to install Traffic Signal Poles and wiring this week. We are waiting for SCE to install service meters for the new proposed traffic signal & lighting system. Please observe construction warning signs. Thank you for your cooperation and understanding.