De Portola Road Drainage - Weekly Status

We are continuing with the construction of the De Portola Road Drainage Improvements project between Shiraz Way and approximately 650 feet northerly in the Temecula Valley Wine Country area within the Community of Rancho California of Riverside County. Crews are currently working on the new proposed retaining wall.


Note: There are multiple construction projects on De Portola Road (Rancho Water District, Eastern Municipal Water District, and County of Riverside). Please observe construction warning signs, follow traffic control staff’s directions, and use caution while travelling through. Thank you for your patience and understanding.

Steven Gray
A Street & Nuevo Road Resurfacing - Weekly Status - Week of May 19th

We’re pleased to announce that paving, striping, and signage installation have been completed on A Street (from Nuevo Road to Harvill Avenue) and on Nuevo Road (from A Street to approximately 1,472 feet south of A Street) in the Community of Mead Valley, Riverside County.

In the coming week, the contractor will install the remaining traffic signal backplates. The project is on track for full completion by next week.

Thank you for your continued patience, understanding, and cooperation throughout the duration of this project.

Yvette MunozA street
Skyview Pedestrian Bridge - Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles.

The contractor is working on the bridge substructure (supporting reinforced concrete columns).



Estimate completion: Summer 2026

No traffic impact. Will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.



You're Invited! Mecca Neighborhood Park and Greening Project GROUNDBREAKING CEREMONY

You’re Invited to the Mecca Neighborhood Park and Greening Project GROUNDBREAKING CEREMONY.
Tuesday, May 20, 2025 at 6:00PM .

Yvette MunozMecca
Good Hope Area and Theda Street - Weekly Status

Good Hope Area and Theda Street - Weekly Status

We are continuing with the construction of sidewalks and repairing roads at Steele Peak Drive, Palm Street, Mountain Avenue, and Theda Street in Good Hope Community area. Currently, the contractor is working on Theda Street from Mountain Road to Ellis Avenue. The roadway is narrow. Please slow down and observe construction warning signs while travelling through. Thank you for your patience and understanding.

Steven Gray
De Portola Road Drainage

We continue with the construction of the De Portola Road Drainage Improvements project between Shiraz Way and approximately 650 feet northerly in the Temecula Valley Wine Country area within the Community of Rancho California of Riverside County. Contractor is currently working on new proposed retaining wall.  

 Note: There are multiple construction projects on De Portola Road (Rancho Water District, Eastern Municipal Water District, and County of Riverside). Please observe construction warning signs, follow traffic control staff’s directions, and use caution while travelling through. Thank you for your patience and understanding.

Yvette Munozdeportola
Pauba Road and De Luz Road - Weekly Status

Pauba Road Widening: Crews are continuing the road improvements on Pauba Rd between Via Del Monte and Calle Contento. The contractor is constructing various retaining walls along Pauba Road. Pauba Road will be reduced to one lane with flagging operations during working hours.



De Luz Road Culvert Replacement: The contractor is resuming work replacing multiple culverts on De Luz Rd. At the intersection of De Luz Rd and Rancho California Rd, both roads will be reduced to one lane with flagging operations during working hours.



Please observe construction warning signs, use caution, and follow traffic control staff’s directions. Thank you for your patience and understanding.



Steven GrayPauba
Skyview Road Pedestrian Bridge - Weekly Status

Skyview Road Pedestrian Bridge - Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles.

The contractor currently working on the bridge substructure (supporting reinforced concrete columns).

Estimate completion: Summer 2026

No traffic impact. Will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.

Jurupa Grade Separation - Construction Alert - Week of 5/12

⚠️ CONSTRUCTION ALERT⚠️


Week of May 12, 2025
Single lane closures are planned on northbound Van Buren Boulevard over the next two weeks—please use alternate routes.

 

TRAFFIC IMPACTS:
Northbound Van Buren Blvd (north of Limonite Ave to south of Jurupa Rd)
Wednesday, May 14
Monday–Friday, May 19–22
5 a.m. to 4 p.m.

- Closure needed for ongoing construction and oversized truck deliveries

- Crews continuing work on the railroad track

- Reduce speeds and watch for large trucks in and out of the project area

 

This information may change due to weather or field conditions.

Plan ahead, expect delays, and use alternate routes when possible.

 

Construction Hotline: 800-679-9570
More info: www.JurupaGradeSeparation.com

#JurupaGradeSeparation #JurupaValley #JurupaValleyTraffic

Good Hope Area and Theda Street - Weekly Status

We are continuing with the construction of sidewalks and repairing roads at Steele Peak Drive, Palm Street, Mountain Avenue, and Theda Street in Good Hope Community area. Currently, the contractor is working on Theda Street from Mountain Road to Ellis Avenue. The roadway is narrow. Please slow down and observe construction warning signs while travelling through. Thank you for your patience and understanding.

Steven Gray
Skyview Road Pedestrian Bridge - Weekly Status

We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles.

The contractor currently working on drainage systems and preparing to start the bridge construction.



Estimate completion: Summer 2026

No traffic impact. We will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.



Grand Avenue Sidewalk - Weekly Status

We are continuing the construction of sidewalk on Grand Avenue from Adelfa Street to Blackwell Boulevard and along the north side of Grand Avenue between Brechtel Street and Corydon Road. It is anticipated to complete in June 2025. Crews are working on concrete curb & gutter, sidewalk and preparing for the roadway reconstruction. Please observe construction warning signs and use caution while traveling through. Thank you for your patience and understanding.



Note: The roadway is narrowed and shifted during working hours. Please use caution and share the road.



Steven Gray