Clinton Keith Road - VIDEO Alert Update 1/23-1/27

The proposed Clinton Keith Road work from Leon Road to Winchester Road has slowed, and construction is resuming due to rain events. The contractor is continuing to work on the construction of proposed “Arch Culvert” near Leon Road and French Valley Creek Bridge. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.

Lincoln Street Weekly Update- Week of 1/16/22

We completed the removal & replacing of existing pavement with new asphalt on Lincoln Street from Indiana Avenue to Magnolia Avenue in the Home Gardens area. The contractor is working on traffic stripe, adjusting manholes to grades, and traffic signal detection system this week. Please use caution and observe warning signs while travelling through the work zone. Thank you for your understanding.

Yvette Munozlincoln
Ramon Road

We completed the resurfacing of Ramon Road from Varner Road to Monterey Avenue in the Thousand Palms area. Thank you for your patience during construction.

Yvette Munoz
Clinton Keith Weekly Update

The proposed Clinton Keith Road from Leon Road to Winchester Road is progressing well. The contractor is actively working on the construction of the “Arch Culvert” near Leon Road. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.

Yvette Munoz
Jurupa Grade Separation Project UPDATE Dec. 12th

#JurupaGradeSeparationProject

 

TRAFFIC FLAGGING: Thursday, Dec. 15, from 7 a.m. to 4 p.m., crews will perform drainage work on Jurupa Detour Road. Crews will direct traffic from the northbound lane to the southbound lane. Please drive with caution through the area. 

 

SUBSCRIBE: to WEEKLY UPDATES

http://www.JurupaGradeSeparation.com

FOLLOW & SHARE: IG @jurupagradeseparation and on Fb @Jurupa Grade Separation Project

 

BUSINESS DIRECTORY:

https://www.jurupagradeseparation.com/business-directory/

BUSINESS ACCESS REMAINS OPEN at ALL Felspar St. and Jurupa Rd. business plazas.

SHOP #ShopLocalJurupaValley #ShopJV #ShopJurupaValley 

 

#RivCoTrans 

#JurupaGradeSeparation 

#CityofJurupaValley

#JurupaValley

#ConnectingJurupaValley 

#BuildingBridges 

#ConnectingCommunities 

#RivCo

Steven GrayJurupaGrade
LINCOLN STREET UPDATE Week of Dec. 12th

LINCOLN STREET UPDATE from Indiana Avenue to Magnolia Avenue in the Home Gardens area. Due to contractor’s conflicting work schedule, the contractor is scheduled to remove existing asphalt pavement and pave new asphalt starting Today December 12, 2022. The road surface around all new concrete cross gutters and curb ramps are rough/uneven. Please use caution and observe warning signs while travelling through the work zone.

Steven Graylincoln
Clinton Keith Road - Weekly Update Video

The contractor is continuing the preparation for the placement of concrete to proposed bridge over French Valley Creek, importing soil for the proposed Clinton Keith Road from Leon Road to Winchester Road. In addition, Murrieta Marketplace’s contractor is continuing the installation of sewer line crossing under Winchester Road at Benton Road. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.

HAMNER AVE BRIDGE PROJECT Update

#HamnerAveProject

 

EXPANDED WORK HOURS

Saturday | Dec. 3 & 10  | 6 a.m. -  3:30 p.m. 

Saturday work planned on the western span of the new bridge and on the bridge approach at the south end.  

 

NEW TRAFFIC PATTERN COMING SOON

Crews are working toward opening the western span of the new bridge and shifting both north and southbound traffic onto it in mid-December. Multiple tasks must be completed with acceptable weather conditions to meet this schedule or the operation will be postponed until mid-January. 

 

CHECK OUT the project website and social media for updates and details the week of Dec. 5. 

 

SUBSCRIBE for updates: https://www.hamneraveproject.com/updates/

IG:@hamneraveproject

FB: Hamner Avenue Bridge and Widening Project

 

#RivCoTrans 

Thank You-->#NorcoCA #Eastvale 

Crews continue #BuildingBridges #ConnectingCommunities #RivCo

Steven GrayHamner
Clinton Keith Rd Phase 3 Construction Notice and Video Update

The contractor is continuing the preparation for the placement of concrete to proposed bridge over French Valley Creek, importing soil for the proposed Clinton Keith Road from Leon Road to Winchester Road. In addition, Murrieta Marketplace’s contractor is continuing the installation of sewer line crossing under Winchester Road at Benton Road. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.

Jurupa Grade Separation Project Construction UPDATE

#JurupaGradeSeparation

 

Check out our latest peek->BEHIND THE K-RAIL 

Crews continue to work on the Van Buren Blvd. bridge and the Jurupa Rd. underpass support systems. #ConnectingJurupaValley #RivCoTrans #ConnectingCommunities #BuildingBridges

 

SUBSCRIBE: 

UPDATES http://www.JurupaGradeSeparation.com

 

FOLLOW & SHARE: 

IG @jurupagradeseparation

on Fb @Jurupa Grade Separation Project

 

SHOP local #ShopLocalJurupaValley #ShopJV #ShopJurupaValley #JurupaValley

 

BUSINESS DIRECTORY:

https://www.jurupagradeseparation.com/business-directory/

 

BUSINESS ACCESS REMAINS OPEN at ALL Felspar St. and Jurupa Rd business plaza's.

Steven GrayJurupaGrade
Hamner Ave. Bridge & Widening Project UPDATE

#HamnerAveProject

 

TRAFFIC CONTROL

Tuesday & Wednesday | Nov. 22 & Nov. 23  | 7 a.m. -  5 p.m. 

NB and SB Hamner Ave. from Detroit Street to Citrus Street. 

Crews will pave on the north and south side of the project. Expect delays and traffic flagging. 

 

 

NEW TRAFFIC PATTERN COMING SOON

Once paving operations are complete on the north and south side bridge approaches and the road widening sections, crews will continue to work on the final touches of the western bridge span. The western bridge span will open to motorists and traffic will switch tentatively in mid-December. Check the project website and social media for details. The existing Hamner Avenue Bridge will be retired, and crews will begin the construction of the eastern bridge span. The project is tentatively scheduled to be complete by the summer of 2024.

 

SUBSCRIBE for updates: Sign Up for Updates

 

#RivCoTrans #NorcoCA #Eastvale #BuildingBridges #ConnectingCommunities #RivCo.

Steven GrayHamner