The Clinton Keith Road Extension Project from Leon Road to Winchester Road is slowly progressing due to recent rain events and site conditions. The contractor will resume this week permitting weather conditions with planned construction activities such as French Valley Creek Bridge, installation of Arch Culverts, drainage systems, traffic signal systems, and new roadway structure including Winchester Road widening. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.
The contractor has installed nearly 40% of the median and will continue to work easterly from Nuevo to Bridge Street. We will continue the construction from Lakeview Avenue to Bridge Street with a lane Closure Nightly from 8:00 PM until 5:00 AM (weather permitting). Please use caution due to the newly raised median and obey traffic control personnel while traveling through the area. #ramonamedian
***No work scheduled Monday, 3/20 to Wednesday 3/22 due to rain. Will resume Thursday 3/23 night and continue on Friday and Sunday nights.
East Hemet & Valle Vista:
WORK RESUMES
March 23
Please watch for traffic control operations.
Girard St. and Acacia Ave. Projects
Monday - Friday & possibly Saturdays
7 a.m. - 6 p.m.
Stetson Ave. Project
Monday - Friday
7 a.m. - 6 p.m.
WEATHER PERMITTING
The contractor is continuing with the Slurry Seal project for District 4 and 5 (From Thermal to Cabazon) with crack sealing and pavement repair. The contractor is preparing for the slurry seal application soon. Please visit our Transportation website for more information regarding Slurry Seal applications. www.rcprojects.org/slurryseal
The contractor started with the Slurry Seal project on various streets in District 1 and 2 (From Lake Elsinore to Corona) with weed abatement, crack sealing and pavement repair. The contractor is preparing for the slurry seal application soon. Please visit our Transportation website for more information regarding Slurry Seal applications. https://rcprojects.org/slurryseal
Work planned for Saturday, March 18th
Work planned for Saturday, March 18th
Our crews continue to work in #EastHemet and #ValleVista next week, weather permitting. #GirardStProject #StetsonAveProject #AcaciaAveProject Monday - Saturday | 7 a.m. - 6 p.m. http://RCProjects.org Construction Hotline: 877-277-5343
WEATHER PERMITTING...
#RivCoTrans #ramonamedian
#RamonaExpressway work continues:
ONE LANE AVAILABLE TO TRAFFIC WITH PILOT CAR ESORTS
LANE CLOSURE REMAINS IN PLACE:
NIGHTTIME WORK--> 8 p.m. to 5 a.m. the following morning
THIS WEEK--> Sunday, March 12 to Thursday, March 16 and possibly Friday, March 17
CONTINUES WEEKLY--> SUN.-THURS & POSSIBLY FRI. THROUGH EARLY APRIL
SPEED LIMIT -->35 MPG
>>>USE ALTERNATE ROUTES<<<
-->ADD ADDITIONAL TIME FOR TRAVEL
www.RCProjects.org/RamonaMedian
Construction Hotline: 877-277-5343
Ramona Expressway is now open in both directions. Thanks for your patience and please reduce speed and drive with caution through the the construction zone.
Construction on Ramona Expressway is expected to be finished after 8:15 a.m. this morning and the road will be open in both directions. We apologize for the delay in opening Ramona Expressway at 5 a.m. as planned due to unexpected field conditions. Construction will continue nightly through Thursday night from 8 p.m. to 5 a.m. Thank you for your patience.
The contractor is ready to start the construction for Ramona Expressway Median from Rider Street (3/4 Miles east) towards Warren Road in the Community of Nuevo, Lakeview, and Gilman Springs.
Construction schedule next week: Sunday, March 5 at 8:00 PM until Friday, March 10 at 5 AM. Lane Closure Nightly from 8:00 PM until 5:00 AM.
Please use caution and obey traffic control personnel while travelling through the area.
The contractor started the Slurry Seal project for District 4 and 5 (From Thermal to Cabazon) with pavement repair, weed abatement, and concrete work. We are preparing for the slurry seal application soon. Please visit our Transportation website for more information regarding Slurry Seal applications.
Some of the existing concrete cross-gutter, spandrels, and curb ramps on Stetson Avenue have been replaced . We will continue the concrete placement work on Stetson Avenue from Evelyn Way towards Stanford Avenue in the East Hemet area. Please use caution, observe construction warning signs, and expect a little delay while travelling through the area. Thanks you for your patience.
The proposed Clinton Keith Road from Leon Road to Winchester Road is continuing with various construction activities such as French Valley Creek Bridge, installation of Arch Culverts, drainage systems, and a new roadway structure including Winchester Road widening. Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.