Ramona Expressway Median - Weekly Status

The contractor completed about 65% of new proposed concrete median for Ramona Expressway Median from Rider Street (3/4 Miles easterly) towards Warren Road in the Community of Nuevo, Lakeview, and Gilman Springs. We will continue the construction from Bridge Street towards Warren Road with a lane Closure Nightly from 8:00 PM until 5:00 AM (weather permitting). Please use caution due to new raised median and obey traffic control personnel while travelling through the area.

Steven Grayramonamedian
Girard St Project Road Closures continue

#GirardStProject in East Hemet

ROAD CLOSURES CONTINUE:

Girard Street

BETWEEN Stetson and Johnston avenues

AND Mayberry and Acacia avenues

USE San Jacinto Avenue or Yale Street as alternate routes.

Monday - Friday & possibly Saturday -->WEATHER PERMITTING

7 a.m. - 6 p.m.

WATCH FOR TRAFFIC CONTROL one lane may be available on other parts of the street.

Project Area: Girard Street from the Ramona Bowl Gates to the County line near Melrose Avenue. 

rcprojects.org/girardstreet

Yvette Munozgirardst
Girard Street Road Closures

#GirardStProject
ROAD CLOSURES:

Girard Street

BETWEEN Stetson and Johnston Avenues

AND Mayberry and Acacia Avenues

Monday - Friday & possibly Saturdays

7 a.m. - 6 p.m.

WATCH FOR TRAFFIC CONTROL, one lane may be available on other parts of the street.

Project Area: Girard Street from the Ramona Bowl Gates to the County line near Melrose Avenue.

USE alternate routes.

WEATHER PERMITTING

rcprojects.org/girardstreet

Yvette Munozgirardst
Slurry Seal Project Update, Districts 1 & 2

Slurry Seal Project Update- Districts 1 & 2 - Delayed start due to recent rain events. Work will resume on various streets in Lake Elsinore & Corona with weed abatement, crack sealing, curb ramps, and pavement repair. Please visit rcprojects.org/slurryseal for more info

Yvette Munozslurryseal
Communities of East Hemet & Valle Vista Construction Update, Week of March 27

East Hemet & Valle Vista:

WEEK OF MARCH 27

Please watch for traffic control operations.

#GirardStProject

Girard St. Project

Monday - Friday & possibly Saturdays

7 a.m. - 6 p.m.

WATCH FOR TRAFFIC CONTROL, one lane may be available.

USE alternate routes.

WEATHER PERMITTING

rcprojects.org/girardstreet

#AcaciaAveProject

Acacia Ave. Project

Monday - Friday & possibly Saturdays

7 a.m. - 6 p.m.

WATCH FOR ROAD CLOSURE, and parking restrictions.

WEATHER PERMITTING

rcprojects.org/girardstreet

#StetsonAveProject

Stetson Ave. Project

Monday - Friday

7 a.m. - 6 p.m.

EXPECT DELAYS, use alternate routes.

WEATHER PERMITTING

rcprojects.org/stetson-ave-resurfacing

#ConnectingCommunities

#RivCoTrans

www.RCProjects.org

Clinton Keith Construction Notice, week of March 27

The Clinton Keith Road Extension Project from Leon Road to Winchester Road is slowly progressing due to recent rain events and site conditions. The contractor will resume this week permitting weather conditions with planned construction activities such as French Valley Creek Bridge, installation of Arch Culverts, drainage systems, traffic signal systems, and new roadway structure including Winchester Road widening.  Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.

Embed Block
Add an embed URL or code. Learn more
Yvette Munoz
Ramona Expressway Median project update, March 21, 2023

The contractor has installed nearly 40% of the median and will continue to work easterly from Nuevo to Bridge Street. We will continue the construction from Lakeview Avenue to Bridge Street with a lane Closure Nightly from 8:00 PM until 5:00 AM (weather permitting). Please use caution due to the newly raised median and obey traffic control personnel while traveling through the area.  #ramonamedian

***No work scheduled Monday, 3/20 to Wednesday 3/22 due to rain. Will resume Thursday 3/23 night and continue on Friday and Sunday nights.

Girard Street, Acacia Ave & Stetson Ave UPDATE

East Hemet & Valle Vista:

#GirardStProject

#AcaciaAveProject

#StetsonAveProject

WORK RESUMES

March 23

Please watch for traffic control operations.

Girard St. and Acacia Ave. Projects

Monday - Friday & possibly Saturdays

7 a.m. - 6 p.m.

Stetson Ave. Project

Monday - Friday

7 a.m. - 6 p.m.

WEATHER PERMITTING

www.RCProjects.org

Steven GrayGirardSt
Slurry Seal, Districts 4 & 5, Weekly Update March 20, 2023

The contractor is continuing with the Slurry Seal project for District 4 and 5 (From Thermal to Cabazon) with crack sealing and pavement repair. The contractor is preparing for the slurry seal application soon. Please visit our Transportation website for more information regarding Slurry Seal applications. www.rcprojects.org/slurryseal

Yvette Munozslurryseal
Slurry Seal, Districts 1 & 2, Weekly Update - March 20, 2023

The contractor started with the Slurry Seal project on various streets in District 1 and 2 (From Lake Elsinore to Corona) with weed abatement, crack sealing and pavement repair. The contractor is preparing for the slurry seal application soon. Please visit our Transportation website for more information regarding Slurry Seal applications. https://rcprojects.org/slurryseal

Yvette Munozslurryseal
Ramona Expressway lane closure

WEATHER PERMITTING...

#RivCoTrans #ramonamedian

#RamonaExpressway work continues:

ONE LANE AVAILABLE TO TRAFFIC WITH PILOT CAR ESORTS

LANE CLOSURE REMAINS IN PLACE:

NIGHTTIME WORK--> 8 p.m. to 5 a.m. the following morning

THIS WEEK--> Sunday, March 12 to Thursday, March 16 and possibly Friday, March 17

CONTINUES WEEKLY--> SUN.-THURS & POSSIBLY FRI. THROUGH EARLY APRIL

SPEED LIMIT -->35 MPG

>>>USE ALTERNATE ROUTES<<<
-->ADD ADDITIONAL TIME FOR TRAVEL

www.RCProjects.org/RamonaMedian

Construction Hotline: 877-277-5343

Yvette Munoz