Stetson Avenue Resurfacing - Weekly Status

The contractor completed the replacement of existing asphalt pavement including driveway tie-in and AC Dikes on Stetson Avenue from Hemet Street to Santa Fe Street in the East Hemet. We are working on new traffic stripe, roadside signs, manholes adjustment, and other minor work. Please continue to use caution, observe construction warning signs, and expect delays while travelling through the area. Thank you for your understanding and patience.

Clinton Keith Rd Construction Notice and Video May 1st- 5th 2023

The proposed Clinton Keith Road from Leon Road to Winchester Road is continuing to progress as planned. The contractor is working on importing material for the roadway structure, construction of Arch Culverts, SR -79 (Winchester Road) widening, traffic signal systems, and French Valley Creek Bridge Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.

Slurry Seal FY 22-23 Dist. 1 & 2 - Weekly Status

Lake Elsinore area: Begin slurry seal application to neighborhood streets.

Coronita area: Completed crack seal to existing asphalt pavement to various streets and begin slurry application.

Home Gardens area: Crack sealing and repairing existing pavement.

Woodcrest area: Repair & prepare existing asphalt pavement for slurry seal application.

Please follow construction warning signs and DO NOT park vehicles on street with posted “NO PARKING” signs. Thank you for your cooperation and understanding.

Please visit our Transportation website for more information regarding Slurry Seal applications. www.rcprojects.org/slurryseal

Jurupa Grade Separation alternating lane closures

#JurupaGradeSeparationProject

ALTERNATING LANE CLOSURES

Van Buren Blvd. from Jurupa Connector Rd. to 52nd St.

Tuesday, May 2 from 8:45 a.m. - 3 p.m.

CIERRES DE CARRILES ALTERNATIVOS

Bulevar Van Buren. de Jurupa Connector Rd. a la calle 52

Martes 2 de mayo de 8:45 a.m. - 3:00 p.m.

SUBSCRIBE | SUSCRIBIR

http://www.JurupaGradeSeparationProject.com

CONNECT | CONECTAR

IG: @jurupagradeseparation

FB: @Jurupa Grade Separation Project

REMINDER | RECORDATORIO --> #ShopJV #comercioJV

BUSINESS DIRECTORY | DIRECTORIO DE NEGOCIOS

Business Directory - Jurupa Grade Separation Project

#ShopLocalJV #SHOPJurupaValley

Yvette Munoz
Girard Street is Open

#EastHemet #GirardStProject

Girard Street is OPEN

RAMONA BOWL EVENT:
From E. Florida Ave. USE Girard St.

Crews continue to work on the shoulder until project completion.
Monday - Friday, 7 a.m. - 6 p.m.

We are working on finalizing the construction of Girard Street in the east Hemet area. Please continue to use caution while traveling through the area. Thank you for your understanding and patience.

Video Block
Double-click here to add a video by URL or embed code. Learn more
Yvette Munozgirardst
Stetson Ave project work continues

The contractor is scheduled to complete the replacement of existing asphalt pavement on Stetson Avenue from Hemet Street to Santa Fe Street in the East Hemet area this Monday 5/1/23. We are working on new traffic stripe, manhole adjustments, asphalt dike, and other minor work. Please continue to use caution, observe construction warning signs, and expect delays while traveling through the area. Thank you for your understanding and patience.

#EastHemet

#StetsonAveProject

Crews continue paving work today, Friday, April 28 and Monday, May 1 from 7 a.m. to 6 p.m.

Expect delays and please use Johnston Avenue as an alternate route.

Friday: from Madison Ct. to near San Jacinto St.

Monday: from San Jacinto St. to Santa Fe St. (end of project limit

Clinton Keith

The proposed Clinton Keith Road extension from Leon Road to Winchester Road is progressing as planned. The contractor is working on importing material for the roadway structure, building the concrete headwall of Arch Culverts, and concrete curb and sidewalk, traffic signal systems, and a new roadway structure including Winchester Road widening.  Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.

Yvette Munoz
Viejo Drive Gully Repair - Weekly Status

The contractor resumed the construction of the newly proposed drain and slope/gully on Grant Avenue in the Valle Vista Community. The project was on hold due to conflicts with actual field conditions. There is no major impact to traffic. Please be aware of trucks traffic on Grant Avenue south of Florida Avenue during normal working hours.

 

Yvette Munoz
Girard Street Resurfacing, Caroline & Rosalie, Valle Vista Library, and Acacia Ave Drainage - Weekly Status

We completed the replacement of the existing pavement on Girard Street from Ramona Bowl Entrance to Florida Avenue in the East Hemet area.  The contractor is currently working on the shoulder, an asphalt Dike, tie-in asphalt driveways, and pavement delineations. Please continue to use caution while traveling through the area. Thanks you for your understanding and patience.

Yvette MunozGirardSt
Slurry Seal FY 22-23, Dist. 4 & 5 - Weekly Status

The contractor completed slurry seal application, including all pavement delineations, to Desert Hot Springs area, Airport Blvd. (Thermal area), and Cabazon area. The project is temporarily suspended until May 14, 2023 due to low temperature at night for Reche Vista Drive, Reche Canyon Road and Gilman Hot Springs Road. Please visit our Transportation website for more information regarding Slurry Seal applications. www.rcprojects.org/slurryseal

Yvette Munozslurryseal
Slurry Seal FY 22-23 Dist 1 & 2 - Weekly Status

Lake Elsinore area: Completed application of new slurry seal to Audelo Street, Patrick Court, and Monty Court on Saturday April 22, 2023. Scheduled to apply new slurry seal to neighborhood streets.

Coronita area: Continue to crack seal existing asphalt pavement on various streets and begin slurry application. Slurry Seal application for Paseo Grande Road was scheduled on Saturday, April 22, 2023 (partial completed and to be scheduled to complete to accommodate school traffic).

Home Gardens area: Completed replacement of concrete curb ramps.

Woodcrest area: Repair & prepare existing asphalt pavement for slurry seal application.

Please follows construction warning signs and DO NOT park vehicles on street with posted “NO PARKING” signs. Thank you for your cooperation and understanding.

Please visit our Transportation website for more information regarding Slurry Seal applications. www.rcprojects.org/slurryseal

Yvette Munozslurryseal
Work continues in East Hemet


#EastHemet

#StetsonAveProject 

#GirardStProject

RAMONA BOWL EVENT:

From E. Florida Ave. PLEASE USE San Jacinto St. to Stetson Ave. to Girard St. 

OR Stetson Ave. to Girard St.

Crews continue to work on pavement improvements in the area.

Monday - Friday and possibly Saturday 7 a.m. - 6 p.m.

Ramona Expressway Median COMPLETE!

The contractor completed new proposed concrete median for Ramona Expressway Median from Rider Street (3/4 Miles easterly) towards Warren Road in the Community of Nuevo, Lakeview, and Gilman Springs. Please use caution due to new raised concrete median and obey traffic control personnel while travelling through the area. Thank you for your patience and understanding!

#RamonaExpresswayMedianProject

THANKS for your patience during this roadway construction project on Ramona Expressway.

#RivCoTrans installed a 22-inch-wide by 8-inch-high concrete center median on 8.5 miles of #RamonaExpressway from approximately ¾-of-a-mile east of Rider Street on  the west end, to Warren Road on the east end, to improve public safety. 

PLEASE continue to #DRIVEwithCARE #RamonaExpressway. 

NEXT UP: Bridge Street traffic signal installation, coming this summer.

Steven Grayramonamedian