Crews continue with the pavement reconstruction and improvements on Van Buren Blvd. from City of Riverside limits (Pine Court) to Capella Street in the Woodcrest Community of Riverside. Crews completed concrete improvements and traffic signal modifications. We are working on reconstruction of asphalt pavement to side streets and continue with the removal and paving new (asphalt base course) on Van Buren Blvd. this weekend. Please observe construction warning signs, use caution, and follow traffic control staff’s directions. Thank you for your patience and understanding.
Slurry Seal FY24-25 District 1, 2, 3 - Weekly Status
- We finished slurry seal in Morgan Hills and Murrieta Hot Springs area.
- Pavement Markings and the First coat of striping has been completed in the Morgan Hill area.
- Asphalt repairs have been completed throughout the project.
- ADA ramps have been completed throughout the project.
- Contractor will continue with the Crack Treatment with Crack Seal in the Riverside area.
- Contractor will continue with the slurry seal in the Perris area with the first crew.
- The prime contractor will have the second crew perform repair work in Hemet.
- Striping lay out should start this week on Willows, Washington and both Pourroy sections.
- Micro-Milling will start on Wednesday in Hemet and then Thursday and Friday in Temescal Valley.
- Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone.
Thank you for your patience and understanding.
Slurry Seal FY24-25 District 1,2,3 UPDATE
Due to the high temperatures, the crews can’t complete slurry seal schedule as planned in Hemet area.
The streets not being completed today are Collegian Way/ Major DR, Larksong St., Viola ST., Primrose Ln., Lori Lane.
Cancellation notices have been passed out to the residents. Crews will schedule to come back later to slurry the canceled streets.
Crews continue with the pavement reconstruction and improvements on Van Buren Blvd. from the City of Riverside limits (Pine Court) to Capella Street in the Woodcrest Community of Riverside. Work is approximately 90% complete with concrete improvements and traffic signal modifications. Crews are scheduled to work 7 days a week for next three weeks. Please observe construction warning signs, use caution, and follow traffic control staff’s directions. Thank you for your patience and understanding.
Slurry Seal FY24-25 District 1,2,3 - UPDATE
Due to the high temperatures and mechanical issues, the crews can’t complete slurry seal schedule as planned in Hemet area.
The streets not being completed today are Alice Lane, Dixon Dr and Torrey Pine Ct.
Our crews will hand out cancellation notices for streets not completed today. We will schedule to come back later to slurry those streets.
Thank you for your understanding.
Crews are working on repairs on Pourroy Rd from Murrieta Hot Springs to Old Pourroy Rd on Wednesday (Today) and Thursday. Thank you for your understanding.
REMINDER--->> Gilman Springs Road Closure
24/7 ROAD CLOSURE
Begins Saturday morning, Oct. 5 | 6 a.m.
Gilman Springs Rd. will be closed between north of Bridge St. and south of Alessandro Rd. through Nov. 21, 2024. Please use the posted detour.
----------------------------------------------
Gilman Springs Road Actualizacion de el proyecto
CIERRE DE CARRETERAS 24/7
Comienza el sábado 5 de octubre por la mañana | 6 a.m.
Gilman Springs Rd. estará cerrado entre el norte de Bridge St. y el sur de Alessandro Rd. hasta el 21 de noviembre de 2024. Utilice el desvío publicado.
Hotline: 877-277-5343
Website: Rcprojects.org/Gilman
Linea Directa: 877-277-5343
Sitio Web: Rcprojects.org/Gilman
#GilmanSpringsRoad #Riversideconstructionprojects
• We completed the weed abatement and asphalt repair throughout the project in Districts 1,2 and 3.
• We finished slurry seal in Morgan Hills area. Pavement Marking and first coat of striping has been applied in Morgan Hills area. The contractor will come back to apply second coat of striping latter. All BMPs (sandbags) in the area will be removed after striping process is completed.
• The contractor will continue with crack treatment with crack seal in Riverside area. For slurry seal, the contractor has crew#1 works in the Murrieta and Woodcrest area, crew#2 works in the Perris and Hemet area.
• The contractor has concrete crew work in the Highgrove area to repair/reconstruct curb ramps to comply with ADA standard.
• Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.
• We completed slurry seal in the Lake Cahuilla Veterans Regional Park. Striping in the Park was done.
• The contractor continues examining and marking locations to repair asphalt in Palm Springs and Desert Hot Springs area.
• This week, from Monday 9/30/2024 to Friday 10/4/2024, the contractor will continue to replace speed bumps, car stoppers, and signs in Lake Cahuilla Veterans Regional Park per request form Park’s manager.
• The contractor will begin crack treatment with crack seal in Palm Springs and Desert Hot Springs area.
• Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.
Gilman Springs Road Shoulder and Median Widening Project
ROAD CLOSED for 7 weeks beginning Saturday, Oct. 5 through Thursday, Nov. 21, 2024
Gilman Springs Road will be closed from north of Bridge Street to south of Alessandro Boulevard.
Please use the posted detour on Highway 79 and State Route 60.
-----------------------------------------------------------
Proyecto de ampliación del arcén y la mediana de Gilman Springs Road
CARRETERA CERRADA durante 7 semanas desde el sabado 5 de octubre hasta el jueves 21 de noviembre de 2024
Gilman Springs Road estará cerrada desde el norte de Bridge Street hasta el sur de Alessandro Boulevard.
Favor de utilizar el desvío en la autopista 79 hacia la ruta estatal 60.
Hotline:
877.277.5343
Website: Rcprojects.org/Gilman
Linea directa: 877.277.5343
Sitio Web: Rcprojects.org/Gilman
#GilmanSpringsRoad #Riversideconstructionprojects
-----
Slurry Seal FY24-25 District 1, 2, 3 for the week of Monday 9/30/2024 through Friday 10/4/2024 in Riverside, Murrieta, Temecula areas. CREW 1
Jurupa Grade Separation Project | Road Closed Reminder ALERT
REMINDER ROAD CLOSED: The intersection of Jurupa and Pedley roads will be closed until October 4.
TRAFFIC IMPACTS THROUGH FRIDAY OCTOBER 4.
Intersection closed to through traffic at Pedley and Jurupa Roads
Please use posted detour at 54th St. to Agate St.
Business access remains open during construction.
Please plan for delays and reduce speed through the construction area.
Behind the K-Rail | Detras del Krail
Photo: Crews installing storm drainpipes at the intersection of Jurupa and Pedley roads.
Foto: Cuadrillas instalando pipas de drenaje pluviales en la intersección de las carreteras Jurupa y Pedley.
---------------------------------------------------------------------------------------------
CIERRE DE CARRETERA: Espere un cierre total de las carreteras Jurupa y Pedley hasta el 4 de octubre.
IMPACTOS DEL TRÁFICO HASTA EL 4 DE OCTUBRE
Intersección cerrada al tráfico en la intersección de Pedley y Jurupa Roads
Utilice el desvío publicado en 54th St. hacia Agate St.
El acceso comercial permanece abierto durante la construcción.
Planifique los retrasos y reduzca la velocidad en el área de construcción.
Stay up to date with exact details by visiting www.jurupagradeseparation.com
Mantengase actualizado con detalles exactos visitando www.jurupagradeseparation.com
Hotline: 800.679.9570
Linea directa: 800.679.9570