Van Buren Blvd. Resurfacing - Weekly Status

Van Buren Blvd. Resurfacing - Weekly Status


Crews continue with the pavement reconstruction and improvements on Van Buren Blvd. from City of Riverside limits (Pine Court) to Capella Street in the Woodcrest Community of Riverside. Our crews completed concrete improvements, traffic signal modifications, and the bottom layer of new asphalt pavement. We are working on paving new asphalt (top course) on Van Buren Blvd. this week. Please observe construction warning signs, use caution, and follow traffic control staff’s directions. Thank you for your patience and understanding.

Steven GrayVan Buren
Slurry Seal FY24-25 District 4,5 - Weekly Status

Slurry Seal FY24-25 District 4,5 - Weekly Status


- We finished repair/upgrade curb ramp in Hemet area to meet ADA standard.

- The contractor continues to saw-cutting, removing and replacing ADA ramps/spandrels in Thermal and Coachella.

- The contractor continues to seal crack and repair asphalt in Thermal, Cabazon, Palm Desert.

- Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.

Steven Grayslurryseal
Slurry Seal FY24-25 District 1, 2, 3 - Weekly Status

Slurry Seal FY24-25 District 1, 2, 3 - Weekly Status



- We finished slurry seal in Morgan Hills and Murrieta Hot Springs area.

- Pavement Markings and the First coat of striping has been completed in the Morgan Hill area.

- Asphalt repairs have been completed throughout the project.

- ADA ramps have been completed throughout the project.

- Contractor will continue with the crack seal in the Temescal Canyon area and touch up work.

- The prime contractor will continue with post sweeping throughout the project.

- Striping and Pavement Markings will be installed in Murrieta Hot Springs, Perris, and Hemet areas.

- Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.



Steven Grayslurryseal
Gilman Springs Road project, week of October 14

Gilman Springs Road Project , Week of October 14 

 

Behind the K-Rail: Crews are relocating utility poles on Gilman Springs Road. 

 

ROAD CLOSURE REMINDER: Gilman Springs Rd. is closed between north of Bridge St. and south of Alessandro Rd. through Nov. 21, 2024. Please use the posted detour. Resident/business access is available in the closed area with provided pass. 

 

----------------------------------------------------------------------------------------------------- 

 

Detrás del K-RaiGilman Springs Road Project 

Week of October 14 

 

Behind the K-Rail: Crews are relocating utility poles on Gilman Springs Road. 

 

ROAD CLOSURE REMINDER: Gilman Springs Rd. is closed between north of Bridge St. and south of Alessandro Rd. through Nov. 21, 2024. Please use the posted detour. Resident/business access is available in the closed area with provided pass.  

----------------------------------------------------------------------------------------------------- 

 

Detrás del K-Rail: Las cuadrillas trabajan en la instalación de postes de servicios en Gilman Springs Road. 

 

RECORDATORIO DE CIERRE DE CARRETERA: Gilman Springs Rd. estará cerrado entre el norte de Bridge St. y el sur de Alessandro Rd. hasta el 21 de noviembre de 2024. Utilice el desvío publicado. El acceso para residentes/empresas está disponible en el área cerrada con el pase proporcionado. 

 

 

Hotline: 877-277-5343 

Website: rcprojectss.org/Gilman 

 

Linea Directa: 877-277-5343 

Sitio Web: rcprojects.org/Gilman 

 

#GilmanSpringsRoad #Riversideconstructionprojects  

 l: Las cuadrillas trabajan en la instalación de postes de servicios en Gilman Springs Road. 

 

RECORDATORIO DE CIERRE DE CARRETERA: Gilman Springs Rd. estará cerrado entre el norte de Bridge St. y el sur de Alessandro Rd. hasta el 21 de noviembre de 2024. Utilice el desvío publicado. El acceso para residentes/empresas está disponible en el área cerrada con el pase proporcionado. 

 

 

Hotline: 877-277-5343 

Website: rcprojectss.org/Gilman 

 

Linea Directa: 877-277-5343 

Sitio Web: rcprojects.org/Gilman 

 

#GilmanSpringsRoad #Riversideconstructionprojects  

 

Yvette MunozGilman
Jurupa Grade Separation Project UPDATE

Jurupa Grade Separation Project 

 

Construction Alert: Intermittent Lane Closures planned in the intersection of Jurupa and Pedley roads during weekdays from Monday, Oct. 14, 2024, through Friday, Oct. 25, 2024.  

 

TRAFFIC IMPACTS  

Weekdays 

Monday, Oct. 14, through Friday, Oct., 25  

6 a.m. to 3 p.m.  

  

Please reduce speed in the construction area.  

 

Stay up to date with exact details by visiting www.jurupagradeseparation.com   

 

Alerta de construction: Cierres de carriles intermitentes están planificados en las carreteras Jurupa y Pedley los dias laborables desde el lunes, 14 de octubre hasta, el viernes 25 de octubre.  

 

IMPACTOS DEL TRAFICO  

Dias laborales  

Del lunes 14 de octubre al viernes 25 de octubre   

6 a.m. a 3 p.m. 

 

Por favor reduzca la velocidad en el área de construcción. 

 

Manténgase actualizado con detalles exactos visitando www.jurupagradeseparation.com  

  

Hotline: 800.679.9570  

Linea Directa: 800.679.9570  

  

#JurupaGradeSeparation #JurupaValley  

Steven GrayJurupaGrade
Micro Milling on Temescal Canyon ALERT

Micro Milling on Temescal Canyon ALERT


Micro milling that will be done TODAY on Temescal Canyon. From Leroy Rd to 22600 Temescal Canyon. Inside lanes. 8 AM - 5PM.


Travel at reduced speeds and obey Traffic Control devices.


Thank you

Steven Gray
Van Buren Blvd. Resurfacing - Weekly Status

Crews continue with the pavement reconstruction and improvements on Van Buren Blvd. from City of Riverside limits (Pine Court) to Capella Street in the Woodcrest Community of Riverside. Crews completed concrete improvements and traffic signal modifications. We are working on reconstruction of asphalt pavement to side streets and continue with the removal and paving new (asphalt base course) on Van Buren Blvd. this weekend. Please observe construction warning signs, use caution, and follow traffic control staff’s directions. Thank you for your patience and understanding.

Steven GrayVan Buren
Slurry Seal FY24-25 District 1, 2, 3 - Weekly Status

Slurry Seal FY24-25 District 1, 2, 3 - Weekly Status


- We finished slurry seal in Morgan Hills and Murrieta Hot Springs area.

- Pavement Markings and the First coat of striping has been completed in the Morgan Hill area.

- Asphalt repairs have been completed throughout the project.

- ADA ramps have been completed throughout the project.

- Contractor will continue with the Crack Treatment with Crack Seal in the Riverside area.

- Contractor will continue with the slurry seal in the Perris area with the first crew.

- The prime contractor will have the second crew perform repair work in Hemet.

- Striping lay out should start this week on Willows, Washington and both Pourroy sections.

- Micro-Milling will start on Wednesday in Hemet and then Thursday and Friday in Temescal Valley.

- Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone.


Thank you for your patience and understanding.


Steven Grayslurryseal
Slurry Seal FY24-25 District 1,2,3 UPDATE 10/3

Slurry Seal FY24-25 District 1,2,3 UPDATE

Due to the high temperatures, the crews can’t complete slurry seal schedule as planned in Hemet area.

The streets not being completed today are Collegian Way/ Major DR, Larksong St., Viola ST., Primrose Ln., Lori Lane.

Cancellation notices have been passed out to the residents. Crews will schedule to come back later to slurry the canceled streets.

Steven Grayslurryseal
Weekly Update: Van Buren Blvd Resurfacing

Crews continue with the pavement reconstruction and improvements on Van Buren Blvd. from the City of Riverside limits (Pine Court) to Capella Street in the Woodcrest Community of Riverside. Work is approximately 90% complete with concrete improvements and traffic signal modifications. Crews are scheduled to work 7 days a week for next three weeks. Please observe construction warning signs, use caution, and follow traffic control staff’s directions. Thank you for your patience and understanding.

Yvette Munoz
Slurry Seal FY24-25 District 1, 2, 3 - UPDATE

Slurry Seal FY24-25 District 1,2,3 - UPDATE


Due to the high temperatures and mechanical issues, the crews can’t complete slurry seal schedule as planned in Hemet area.

The streets not being completed today are Alice Lane, Dixon Dr and Torrey Pine Ct.

Our crews will hand out cancellation notices for streets not completed today. We will schedule to come back later to slurry those streets.


Thank you for your understanding.

Steven Grayslurryseal
ALERT - Pourroy Rd Repairs

Crews are working on repairs on Pourroy Rd from Murrieta Hot Springs to Old Pourroy Rd on Wednesday (Today) and Thursday. Thank you for your understanding.

Steven Gray
REMINDER-->> Gilman Springs Road Closure

REMINDER--->> Gilman Springs Road Closure  


24/7 ROAD CLOSURE   

Begins Saturday morning, Oct. 5 | 6 a.m.  

Gilman Springs Rd. will be closed between north of Bridge St. and south of Alessandro Rd. through Nov. 21, 2024. Please use the posted detour.  

----------------------------------------------  

Gilman Springs Road Actualizacion de el proyecto   

CIERRE DE CARRETERAS 24/7   

Comienza el sábado 5 de octubre por la mañana | 6 a.m.  

Gilman Springs Rd. estará cerrado entre el norte de Bridge St. y el sur de Alessandro Rd. hasta el 21 de noviembre de 2024. Utilice el desvío publicado.    

Hotline: 877-277-5343  

Website: Rcprojects.org/Gilman    

Linea Directa: 877-277-5343  

Sitio Web: Rcprojects.org/Gilman    

#GilmanSpringsRoad #Riversideconstructionprojects   

Yvette MunozGilman
Slurry Seal FY24-25 District 1, 2, 3 - Weekly Status

• We completed the weed abatement and asphalt repair throughout the project in Districts 1,2 and 3.

• We finished slurry seal in Morgan Hills area. Pavement Marking and first coat of striping has been applied in Morgan Hills area. The contractor will come back to apply second coat of striping latter. All BMPs (sandbags) in the area will be removed after striping process is completed.

• The contractor will continue with crack treatment with crack seal in Riverside area. For slurry seal, the contractor has crew#1 works in the Murrieta and Woodcrest area, crew#2 works in the Perris and Hemet area.

• The contractor has concrete crew work in the Highgrove area to repair/reconstruct curb ramps to comply with ADA standard.

• Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.

Steven Grayslurryseal