Nuevo Area Resurfacing Group - Weekly Status

Crews are continuing road improvements in the Nuevo Community. Throughout the week of 02/18/2025, and crews will continue paving operations within the project limits below:




-12th St from Reservoir Ave to North Dr

-Apricot Ave from Lakeview Ave to North Dr

-13th St from Reservoir Ave to North Dr

-Stalder Ave from Ramona Ave to Lakeview Ave

-North Dr from Nuevo Rd to Lakeview Ave




Access to residential properties will be maintained at all times. Please observe construction warning signs, use caution, and follow traffic control staff’s directions. Thank you for your patience and understanding.




Steven Gray
Oleander Avenue Sidewalk - Weekly Status

We completed about 95% of the road widening and new proposed sidewalk project on Oleander Avenue from Haines Street to Clark Street in the Community of Mead Valley. Crews are working on retaining wall, pavement delineations, and roadside signage. Please observe construction warning signs, use caution, and follow traffic control staff’s directions. Thank you for your patience and understanding.

Steven GrayOleander 2025
Ramon Road Bridge Repair

We are currently repairing pavement damage caused by soil erosion on both sides of Ramon Road, near the Railroad Overcrossing between Varner Road and Bob Hope Drive. The estimated completion date is March 3, 2025. Please be mindful of construction warning signs and exercise caution while driving through the area. We appreciate your patience and understanding.

Traffic impact: Westbound Ramon Road from Varner Road to Bob Hope Drive will be CLOSED for approximately 4 weeks. Eastbound traffic will experience intermittent shifts during construction.

Yvette Munoz
Indiana Avenue, Grant Street, and Harlow Avenue Resurfacing - Weekly Status

We completed pavement reconstruction and concrete improvements on Grant Street, Harlow Avenue, and Indiana Avenue in the Home Gardens area. Crews are continuing work on asphalt dikes, driveways, and other improvements on Indiana Avenue from Grant Street to Hillview Drive. Please observe construction warning signs, use caution, and follow traffic control staff’s directions. Thank you for your patience and understanding.


***Klyne Street from Bedford Canyon Road to Bobbitt Avenue in Corona/El Cerrito area will be closed to through traffic from 2/17/25 to 2/21/25 (weather permitting). Residents access only.

Steven Gray
Gilman Springs Road is OPEN to through traffic in both directions

Gilman Springs Road Project Update 

Gilman Springs Road is OPEN to through traffic in both directions. 

Crews will continue working on miscellaneous tasks to complete the project. 

Actualización del proyecto de Gilman Springs Road  

 ---------------------------------------------------------------------------------------- 

Gilman Springs Road está ABIERTA al tráfico en ambas direcciones.  

Los equipos continuarán trabajando en tareas diversas para completar el proyecto.  

 

Hotline: 877.277.5343 

Website: www.rcprojects.org/gilman 

Línea directa: 877.277.5343  

Sitio web: www.rcprojects.org/gilman 

 

#GilmanSpringsRoad  

Yvette Munozgilmanphase6
Rancho Jurupa Park Weekly Update

The Transportation Department is assisting with the improvement of Rancho Jurupa Park.        

This week, the following was completed:

Asphalt Paving completed in the Day Use Parking area.

Asphalt Paving completed for the Lakeview Campground Road.

 

Yvette Munoz
Oleander Avenue Sidewalk - Project Status

Road Widening and Sidewalk Construction Project on Oleander Avenue

We are continuing the road widening and new sidewalk construction along Oleander Avenue, from Haines Street to Clark Street, in the Community of Mead Valley. Crews are currently working on the installation of new asphalt pavement.

For your safety, please be mindful of construction warning signs, exercise caution, and follow the directions of traffic control personnel. We appreciate your patience and cooperation as we work to improve this important area.

• Traffic impact: Due to grinding and paving operation, traffic will be detoured February 6 & 7, 2025 during working hours (7am to 6pm); Oleander Ave will be closed from Haines St to Clark St.



Steven GrayOleander 2025
Clark St Resurfacing & Sidewalk - Weekly Update

With construction work on the concrete curb and gutter between Martin St and Oleander Ave, small sections of the road are being closed during the day. Drivers are asked to follow detour signs and traffic control staff’s guidance between 7:00 AM and 6:00 PM. It's important for everyone to stay cautious and be aware of the construction zones for safety. Thanks for sharing this update!

Yvette Munozclarkstreet
Nuevo Area Resurfacing Group - Weekly Status

Crews are continuing road improvements in the Nuevo Community. Starting Monday, February 3rd, and will begin pulverizing the existing asphalt concrete pavement on the following limits:

- 12th St from Reservoir Ave to North Dr

- Apricot Ave from Lakeview Ave to North Dr

- 13th St from Reservoir Ave to North Dr

- Stalder Ave from Ramona Ave to Lakeview Ave

- North Dr from Nuevo Rd to Lakeview Ave

Full-road closures on Lakeview Ave are no longer expected. Access to residential properties will be maintained at all times. Please drive with caution when driving on the pulverized asphalt concrete pavement, observe construction warning signs, and follow traffic control staff’s directions. Thank you for your patience and understanding.

Steven Gray
Construction Alert: Week of February 3

Single Lane Closures are planned on Felspar Street at Jurupa Road; business access remains open.

TRAFFIC IMPACTS

One lane on Felspar Street will be closed with traffic shifted to the opposite side of the street.

Wednesday, Feb. 5, at 6 a.m., through Friday, Feb. 14, at 4 p.m.

Please drive with caution and reduce speed through the construction zone.

-------------------------------------------------------------------------------------------

Se planean cierres de carriles únicos en Felspar Street y Jurupa Road; el aceso a negocios permanecera abierto.

IMPACTOS DEL TRÁFICO

Se cerrará un carril en Felspar Street y el tráfico se trasladará al lado opuesto de la calle.

Del miércoles 5 de febrero a las 6 a.m. al viernes 14 de febrero a las 4 p.m.

Conduzca con precaución y reduzca la velocidad en la zona de construcción.

For more information visit: www.jurupagradeseparation.com

Para más información visite: www.jurupagradeseparation.com

Hotline: 800.679.9570

Linea Directa: 800.679.9570

#JurupaGradeSeparation #JurupaValley #JurupaValleyTraffic


Steven GrayJurupaGrade
Gilman Springs Road - UPDATE

PROJECT UPDATE: Gilman Springs Road will open to through traffic on Friday, Feb. 7, by 11 p.m., weather permitting.
Crews will continue working on wildlife fencing and miscellaneous tasks to complete the project.
--------------------------------------------------------------------------------------
ACTUALIZACIÓN DEL PROYECTO: Gilman Springs Road se abrirá al tráfico el viernes 7 de febrero a las 11 p.m., si el clima lo permite.
Las cuadrillas continuarán trabajando en el cercado para la vida silvestre y la lista de pendientes para completar el proyecto.

For updates visit rcprojects.org/gilman
Hotline: 877.277.5343

Para obtener actualizaciones, visite rcprojects.org/gilman
Línea directa: 877.277.5343

Steven Graygilmanphase6
CONSTRUCTION ALERT - Intersection of Jurupa and Pedley Rd

CONSTRUCTION ALERT: The intersection of Jurupa and Pedley roads will remain closed through Saturday, Feb. 1, at 6 p.m., weather permitting. 

 

TRAFFIC IMPACTS 

INTERSECTION REMAINS CLOSED THROUGH 

Saturday, Feb. 1, at 6 p.m.  

The intersection closure was extended due to field conditions. 

Please use the posted detour at 54th Street to Agate Street. 

 

This information may change due to weather or field conditions. 

--------------------------------------------------------------------------------------- 

 

ALERTA DE CONSTRUCCIÓN: La intersección de las carreteras Jurupa y Pedley permanecerá cerrada hasta el sábado 1 de febrero a las 6 p.m., si el clima lo permite.  

 

IMPACTOS DEL TRÁFICO  

LA INTERSECCIÓN PERMANECE CERRADA  

Sábado 1 de febrero a las 6 p.m.   

El cierre de la intersección se extendió debido a las condiciones del campo.  

Utilice el desvío publicado en 54th Street hacia Agate Street.  

  

Esta información puede cambiar debido al clima o las condiciones del campo. 

 

For more information visit www.jurupagradeseparation.com  