CONSTRUCTION ALERT
Alerta de construcción disponible en español en www.JurupaGradeSeparation.com
Week of June 2, 2025
Work continues throughout the project area with ongoing activities including:
- Railroad track installation
- Drainage improvements
- Construction at the intersection of Jurupa Road and Felspar Street
The intersection of Jurupa Road and Felspar Street remains closed. Please use posted detours and alternate routes to navigate the area safely.
Businesses are open during construction. Access to shopping plazas and local businesses is available on Jurupa and Felspar.
This information may change due to weather or field conditions.
Construction Hotline: 800-679-9570
We are continuing with the construction of new proposed sidewalk, cross-gutter, reconstructing asphalt pavement, and other improvements on Steele Peak Drive, Palm Street, Mountain Avenue, and Theda Street in Good Hope Community area. Currently, the contractor is working on Steele Peak Drive. The roadway is narrow. Please slow down and observe construction warning signs while travelling through. Thank you for your patience and understanding.
Pauba Road Widening: Pauba Rd will continue to be closed until further notice between Via Del Monte and Mesa Verde Circle to allow crews to safely excavate the proposed retaining walls areas. Pauba Rd is estimated to reopen on Friday (06/20/2025). Traffic detour route will follow Rancho California Rd. Please DO NOT ENTER “ROAD CLOSED” areas. Please use caution, observe construction warning signs and detour signs, and follow traffic staff’s directions. Thank you for your patience and understanding.
De Luz Road Culvert Replacement: Crews are continuing to replace multiple culverts on De Luz Rd. Roads will be reduced to one lane with flagging operations during working hours at the intersection of De Luz Rd & Rancho California Rd and between Calle Corto & Via Vaquero Rd. Please observe construction warning signs, use caution, and follow traffic control staff’s directions. Thank you for your patience and understanding.
‼️ UPDATED ‼️ CONSTRUCTION ALERT - Week of May 26, 2025
Long-term intersection closure begins and traffic control is planned throughout the project area this week.
TRAFFIC IMPACTS:
⚠️ Long-term intersection closure begins at Jurupa Road and Felspar Street
Tues., May 27, for 18 months | Businesses are OPEN during construction
-Access to the Stater Bros. Shopping Plaza is available from Jurupa Road and Felspar Street
-Access to the shopping plaza west of Felspar Street is available from Felspar Street
-Please use the posted detours
The closure is necessary to perform excavation, construct the railroad bridge, and adjust the intersection grade to connect with the Jurupa Road underpass.
⚠️ Lane closures planned on Van Buren Boulevard outside NB lane
Tues. – Sun. | May 27 – June 1 | 6 a.m. to 6 p.m.
-Outside northbound lane closures planned from 52nd Street to Jurupa Connector Road to accommodate railroad track work
⚠️ Jurupa Connector Road and Van Buren Boulevard traffic signal on flash
Tues. and Wed. | May 27 and 28 | 9 a.m. to 4 p.m.
-Intersection signals will be on flash with traffic control in place to install traffic signal equipment
-All vehicles must STOP at the intersection 🛑
This information may change due to weather or field conditions.
Construction Hotline: 800-679-9570
More info: www.JurupaGradeSeparation.com
#JurupaGradeSeparation #JurupaValley #JurupaValleyTraffic
We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles.
The contractor is working on the bridge substructure (supporting reinforced concrete columns) and preparing to erect falsework (temporary supporting structure for bridge construction).
Estimate completion: Summer 2026
No traffic impact. Will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.
We are continuing with the construction of new proposed sidewalk, cross-gutter, reconstructing asphalt pavement, and other improvements on Steele Peak Drive, Palm Street, Mountain Avenue, and Theda Street in Good Hope Community area. Currently, the contractor is working on Steele Peak Drive. The roadway is narrow. Please slow down and observe construction warning signs while travelling through. Thank you for your patience and understanding.
Pauba Road Widening: Starting Wednesday (5/14/2025), Pauba Rd will be closed between Via Del Monte and Mesa Verde Circle to allow crews to safely excavate the proposed retaining walls areas. Pauba Rd is estimated to reopen on Friday (06/20/2025). Traffic detour route will follow Rancho California Rd. Please DO NOT ENTER “ROAD CLOSED” areas. Please use caution, observe construction warning signs and detour signs, and follow traffic staff’s directions. Thank you for your patience and understanding.
De Luz Road Culvert Replacement: Crews are continuing to replace multiple culverts on De Luz Rd. At the intersection of De Luz Rd and Rancho California Rd, both roads will be reduced to one lane with flagging operations during working hours. Please observe construction warning signs, use caution, and follow traffic control staff’s directions. Thank you for your patience and understanding.
We are continuing with the construction of the De Portola Road Drainage Improvements project between Shiraz Way and approximately 650 feet northerly in the Temecula Valley Wine Country area within the Community of Rancho California of Riverside County. Crews are currently working on the new proposed retaining wall.
Note: There are multiple construction projects on De Portola Road (Rancho Water District, Eastern Municipal Water District, and County of Riverside). Please observe construction warning signs, follow traffic control staff’s directions, and use caution while travelling through. Thank you for your patience and understanding.
We’re pleased to announce that paving, striping, and signage installation have been completed on A Street (from Nuevo Road to Harvill Avenue) and on Nuevo Road (from A Street to approximately 1,472 feet south of A Street) in the Community of Mead Valley, Riverside County.
In the coming week, the contractor will install the remaining traffic signal backplates. The project is on track for full completion by next week.
Thank you for your continued patience, understanding, and cooperation throughout the duration of this project.
We are continuing with the construction of Skyview Road Pedestrian Bridge over French Valley Channel in the Community of French Valley. The bridge will cross a gap along Skyview Road where there is no existing road crossing at French Valley Channel. The bridge will provide a path between the French Valley Library, located on the northwest side of the bridge, and the Susan LaVorgna Elementary School, located at the southeast corner of the intersection of Skyview Road and Via Santiago/Algarve Avenue. It will provide multipurpose access for both pedestrians and bicyclists, with no vehicular travel other than access for emergency vehicles.
The contractor is working on the bridge substructure (supporting reinforced concrete columns).
Estimate completion: Summer 2026
No traffic impact. Will monitor and minimize construction noise to adjacent neighborhood. Thank you for your understanding.
You’re Invited to the Mecca Neighborhood Park and Greening Project GROUNDBREAKING CEREMONY.
Tuesday, May 20, 2025 at 6:00PM .
ALERT
Ave 51st will be closed from Jackson St to Calhoun Steet in the Thermal/Coachella area from Wednesday, May 21 to June 4th, 2025 for power pole replacement and electrical grid upgrades. Access will be granted to local residents only that reside within the closure. For your safety please, use alternative routes. We apologize for the inconvenience.
Crews will continue to construct sidewalks, curbs and gutters.
Crews will continue to construct driveways, on select properties. The contractor will coordinate with the property owners or tenants.
LANE RESTRICTIONS:
Expect to see lane restrictions. Drive slowly and look for cones or other traffic control devices that will keep work areas separate from traffic.