Ramona Expressway at Bridge Street Signal - Weekly Status

The contractor resumed the construction this week due to other emergency construction projects. The traffic signal structures are being constructed. Bridge Street at Ramona Expressway is scheduled to close to through traffic on October 9 and 10 due to major road reconstruction. Please follow Detour signage and observe construction warning signs. Thank you for your cooperation and understanding.

Steven Grayramona
Idyllwild Resurfacing - Weekly Status / CLOSURE REMINDER

We completed all streets in the Idyllwild area and Lawler Alpine Cabins & Park Access Road. The contractor is working on Shoulder improvements, Asphalt Dike, Driveways, and utility facilities adjustments on paved streets (North Circle Drive, South Circle Drive, Saunders Meadow Road, and Fern Valley Road) in the Idyllwild area. Please observe construction warning signs, follow flaggers’ directions, and expect delays while travelling through. We are trying our best to accommodate the traffic while facing challenges due to narrow road conditions. Thank you for your patience and understanding!

Note: Humber Park Trail Head & Fern Valley Road closure begins Sunday, October 1, 2023 for retaining wall and roadway reconstruction. Estimate closure time two weeks. Humber Park is closed.

#IDYLLWILD 
Resurfacing Project 2023

24/7 FULL CLOSURE REMINDER

Fern Valley Road and Humber Park FULL CLOSURE begins on Oct.1 at 6 a.m.


USE alternate trails

#IDY #SpitlerPeakTrail #RamonaTrail #CedarSpringTrail 
#CactusSpringsTrail #DeerSpringsTrail #BlackMountainTrail #MarionMountainTrailhead 

#RiversideCountyIdyllwildParkSystem

 

THANK YOU for your PATIENCE IDY and cooperation during construction. 

Information: RCProjects.org/Idyllwild
Hotline: 877-277-5343

#IdyllwildFire #lilyrock #tahquitzrock #tahquitzcanyon #idyllwildcalifornia #idyllwild 
#garnervalleyca #FernValley #DevilsSlideTrail #humberpark #devilsslidetrail #hiking 
#sanjacintomountains #tahquitzrock #saddlejunction 

Steven GrayIdyllwild
Clinton Keith Road - Weekly Status

The proposed Clinton Keith Road from Leon Road to Winchester Road is progressing as planned. The contractor is continuing with Rock Slope protection, shoulder, drainage systems, concrete (curb, median, driveways, and sidewalk), and traffic signal systems. Murrieta Marketplace’s contractor is continuing with the installation of sewer and water lines along the new proposed Clinton Keith Road and on Benton Road. Please observe construction warning signs and use caution while using Benton Road. Thank you for your patience and understanding!

Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED (NO ACCESS).

Week of September 25, Idyllwild Construction Continues

#IDYLLWILD 
Resurfacing Project 2023

CONSTRUCTION CONTINUES 
Hours: 7 a.m. - 6 p.m. Daily
EXPECT LANE CLOSURES WITH TRAFFIC CONTROL in multiple locations within the Idyllwild community.
ADD EXTRA TIME FOR TRAVEL 
narrow lane widths extend delay times.
PLEASE REDUCE YOUR SPEED in the multiple construction zones. 
Crews continue to perform construction operations in the area including saw cutting, utility adjustments, 
pavement removal, milling, and paving and finishing work.
UPDATE Week of September 25 
South Circle Dr. through Sept. 28
North Circle Dr. through Sept. 28
Fern Valley Rd. roadway work through Sept. 28
Saunders Meadow Dr. through Sept 25
Lawler Alpine Cabins through Sept. 28
Lawler Lodge through Sept. 28
RivCo Maintenance Yard through Sept. 29
FULL 24/7 CLOSURE REMINDER
Fern Valley Road and Humber Park FULL 24/7 CLOSURE beginning Oct.1
USE alternate trails
 #IDY #SpitlerPeakTrail #RamonaTrail #CedarSpringTrail 
#CactusSpringsTrail #DeerSpringsTrail #BlackMountainTrail #MarionMountainTrailhead 

#RiversideCountyIdyllwildParkSystem

THANK YOU for your PATIENCE IDY and cooperation during construction. 
Information: 
RCProjects.org/Idyllwild
Hotline: 877-277-5343
#IdyllwildFire #lilyrock 
#tahquitzrock #tahquitzcanyon #idyllwildcalifornia #idyllwild 
#garnervalleyca #FernValley #DevilsSlideTrail #humberpark #devilsslidetrail #hiking 
#sanjacintomountains #tahquitzrock #saddlejunction 

###

Yvette MunozIdyllwild
Idyllwild Resurfacing Project | Fern Valley Road and Humber Park CLOSURE NOTICE

Fern Valley Road and Humber Park in Idyllwild to be closed for two weeks to motorists, pedestrians and cyclists beginning Sunday, Oct. 1 at 6 a.m.

The planned closure is necessary for public safety while contractors complete road repairs and construct a retaining wall. The narrow roadway and access to Humber Park will be an active construction site blocking all access.

• Parking will not be permitted on Fern Valley Road during the closure.

• Access to businesses and residents will not be impacted.

Trail access from the Humber Park parking lot is closed to Devils Slide Trail, the Pacific Crest Trail (PCT), and the Ernie Maxwell Scenic Trail. To access these trails, use the Ernie Maxwell Scenic Trail trailhead on Tahquitz View Drive. PCT hikers visiting Idyllwild must use the Ernie Maxwell Scenic Trail and Tahquitz View Drive.

Alternate Trails hikers can visit are the Spitler Creek Trail, Ramona Trail, Cedar Springs Trail, Cactus Springs Trail, Deer Springs Trail, Black Mountain Trail, Marion Mountain Trail, and the Riverside County Idyllwild Park System

Steven GrayIdyllwild
Slurry Seal FY 23-24 Dist. 1 & 2 - Weekly Status

Slurry Seal FY 23-24 Dist. 1 & 2 - Weekly Status

We are starting Slurry Seal Treatment to various streets in Woodcrest, Mead Valley, Corona, El Centro, Alessandro, and Temescal Valley in the County Supervisor District 1 & 2. Please use caution while travelling through the work areas. Thank you for your patience and understanding.

Steven Grayslurryseal
Hamner Ave. Project Construction Update Week of September 11th

#HamnerAveProject

 

Check out the latest time lapse video of crews placing concrete on the eastern span of the new Mayor Berwin Hanna Bridge.  

REMINDERS:

REDUCE SPEED to 35 mph and watch for crews working on the shoulder north of Citrus Street and behind k-rail at Detroit Street. Please WATCH for trucks entering and exiting the jobsite at multiple locations. 

 

PEDESTRIAN ACCESS is available on the western side of Hamner Avenue from Schleisman Road to the southern crosswalk at Citrus Street. 

 

NO PEDESTRIAN ACCESS ACROSS THE BRIDGE is available in this phase of the project. 

PLEASE USE RTA @riversidetransit Route003, with stops at Taft Street and Hamner Avenue (northbound), and on Citrus Street west of Hamner Avenue (southbound). Please visit riversidetransit.com for information.

 

SUBSCRIBE at http://www.hamneraveproject.com/updates/ 

STAY CONNECTED on IG @hamneraveproject and on FB @Hamner Avenue Bridge and Widening Project.

Steven GrayHamner
Clinton Keith Road - Weekly Status Sept. 11th - 15th

The proposed Clinton Keith Road from Leon Road to Winchester Road is progressing as planned. The contractor paved new asphalt (bottom layers) from Leon Road to SR-79. The construction drainage systems and concrete (curb, median, driveway, and sidewalk) are also progressing. Subcontractor resumed with the construction of various Traffic Signal systems. Murrieta Marketplace’s contractor is continuing with the installation of sewer and water lines along the new proposed Clinton Keith Road and on Benton Road. Please observe construction warning signs and use caution while using Benton Road.

Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED (NO ACCESS).

Project Update: Ramona Expressway traffic signal

The proposed traffic signal system at Ramona Expressway and Bridge Street in the San Jacinto area is progressing as planned. This project is still on schedule to complete by mid November 2023. Please observe construction warning signs and use caution while travelling through the work area.

There will be a brief closure of Bridge Street (2 days) first week of October. Confirmation to follow.

Yvette Munoz
Project Update: Ramona Expressway at Bridge St Traffic Signal

Construction has started on the proposed traffic signal system at Ramona Expressway and Bridge Street in the San Jacinto area. This project is scheduled to be completed in mid November 2023. Please observe construction warning signs and use caution while traveling through the work area.

Yvette Munoz
Jurupa Grade Separation Project Construction Update

Happy Labor Day Weekend!

Week of September 4

#JurupaGradeSeparationProject

Crews continue utility relocation 

work at the business plaza west of Felspar St.

ALL BUSINESSES REMAIN OPEN

Las cuadrillas continúan con la reubicación de servicios públicos

trabajar en la plaza de negocios al oeste de Felspar St.

TODOS LOS NEGOCIOS PERMANECEN ABIERTOS

#ShopJV BUSINESS DIRECTORY
Business Directory - Jurupa Grade Separation Project

Jurupa Road & Felspar Street BUSINESSES
And Jurupa Road & Pedley Road BUSINESSES

--> USE JURUPA RD. DETOURS
--> Van Buren Blvd. to Rutile St. to Galena St. to Felspar St. 

OR Van Buren Blvd. to Pedley Rd. to Jurupa Rd.
#CleanersPlus 
#DoninosJV 
#DonutTyme ->We have BOBA
@drtoothdentalandortho
@elcorralbajagrillinc 
@familydiscount.jurupa 
#FMIRealtyServices 
#HiDefInc
#JackintheBoxJV 
@jdmissionsteakhousejv
#LuckyWokJV 
#MariesBeautySalon 
#MetrobyTMobileJV 
#MomiasNursery
#PanaderiaJaliscoBakery 
@pizzakingjurupa 
@plazaliquor1
@ southridgecycling 
#StateFarmTroyManning 
#StaterBrosJV 
#SubwayJV 
#TitosSmogCheckStarStation
#YourHairCenter 

And Jurupa Road & Rutile Street BUSINESSES
--> USE  JURUPA RD. DETOURS 
--> Van Buren Blvd. to Jurupa Connector Rd. 

OR Rutile St.
#ArmandosRadiatorandMuffler 
#JurupaDairyandGasPropaneRefill
@perezmarket_est1994 

Steven GrayJurupaGrade
IDYLLWILD Resurfacing Project 2023 Update

#IDYLLWILD

Resurfacing Project 2023

 

Construction Continues: August 23

Hours: 7 a.m. - 6 p.m. Daily

 

Expect lane closures with traffic control in the Idyllwild community on South Circle Drive through September 1. 

Please ADD EXTRA TIME FOR TRAVEL and REDUCE YOUR SPEED in the construction zone. 

Crews have been performing construction activities in the area; saw cutting, utility adjustments, pavement removal, milling, and paving. We appreciate your patience and cooperation during construction. 

 

Information: RCProjects.org/Idyllwild

Hotline: 877-277-5343

 

#IdyllwildFire #lilyrock #tahquitzrock #tahquitzcanyon #idyllwildcalifornia #idyllwild #garnervalleyca #FernValley #DevilsSlideTrail #humberpark #devilsslidetrail #idyllwild #hiking #sanjacintomountains #tahquitzrock #saddlejunction

Steven GrayIdyllwild
Clinton Keith Road - Weekly Status

The proposed Clinton Keith Road from Leon Road to Winchester Road is continuing to progress as planned. The contractor is actively installing geofabric (Tensar) and aggregate base from Leon Road to French Valley Bridge, construction drainage systems, and preparing for SR-79 (Winchester Road) widening. Murrieta Market Place’s contractor is continuing with the installation of sewer and water lines along the new proposed Clinton Keith Road and on Benton Road.

Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED.

IDYLLWILD Resurfacing Project 2023 Construction Continues: Week of August 21

#IDYLLWILD

Resurfacing Project 2023

 We are starting to remove and replace existing asphalt pavement on Saunders Meadow Road, then move on to South Circle Drive in the Idyllwild area. Please expect delays while travelling through. We are trying our best to accommodate the traffic while facing challenges due to narrow road conditions. Thank you for your patience and understanding!

Note: The project is 90 Calendar Days. Contractor is authorized to work on weekend.

Construction Continues: Week of August 21

Hours: 7 a.m. - 6 p.m. Daily

Expect lane closures with traffic control in the Idyllwild community on Saunders Meadow Dr. 

Please add extra time for travel and REDUCE YOUR SPEED in the construction zone. 

Crews have been performing construction activities in the area; saw cutting, utility adjustments, pavement removal, milling, and paving. We appreciate your patience and cooperation during construction. 

 

Information: RCProjects.org/Idyllwild

Hotline: 877-277-5343

 

#IdyllwildFire #lilyrock #tahquitzrock #tahquitzcanyon #idyllwildcalifornia #idyllwild #garnervalleyca #FernValley #DevilsSlideTrail #humberpark #devilsslidetrail #idyllwild #hiking #sanjacintomountains #tahquitzrock #saddlejunction

 

Steven GrayIdyllwild